9

(2) Before the first fuel-loading and test-running,

(3)

a

"Final Safety Analysis Report" must be submitted. After the Report is duly examined and approved, an "Approval letter for fuel-loading" will be issued

and only with this approval letter can the

test-running be started.

a

Before formal commissioning of the nuclear plant,

"Revised Final Safety Analysis Report" must be submitted. After this Report is duly examined and

approved, the authority concerned will issue a "Nuclear Installation Operation Licence" and the plant can formally start operation.

To cater for the needs of the Guangdong Nuclear Power

Station, NNSA has enacted the "Provisional Safety Assessment

Regulations for the Guangdong Nuclear Power Station" before promulgation of the

the above-mentioned management regulations.

fundamental principles and assessment procedures of both regulations are the same.

The

Safety Analysis Reports (including the three versions of Preliminary, Final and Revised Final) are the main technical documents submitted by the

the operating unit of a nuclear power plant to NNSA for evaluation of nuclear safety. According to general practice, NNSA will ask the Guangdong Nuclear Power Joint Venture Company (GNPJVC) to prepare the Safety Analysis Reports in conformity with the format specified in Regulatory Guide 1.70

of the US Nuclear Regulatory Commission (but the safety regulations, guidelines and standards mentioned therein can be substituted by corresponding regulations, guidelines and standards promulgated by the supplying country of the nuclear

Share This Page