HITHERTO :

CONFIDENTIAL

58961 - 1

5.

THAT WE HAVE NO REASON WHATSOEVER TO DOUBT THAT THE

DESIGN AND CONSTRUCTION OF THE DAYA BAY PLANT WILL BE TO

A FULLY ACCEPTABLE STANDARD OF SAFETY. HAD WE SEEN ANY

REASON TO DOUBT THIS IN THE COURSE OF OUR EXCHANGES WITH THE

FRENCH AND CHINESE GOVERNMENTS, WE WOULD NATURALLY HAVE

TAKEN THE MATTER UP WITH THEM.

AND

IT IS NOT POSSIBLE TO SPEAK AT THIS STAGE WITH THE SAME

CONFIDENCE ABOUT THE OPERATION OF THE STATION, SINCE SAFETY IN THAT PHASE DEPENDS PARTLY ON ARRANGEMENTS FOR MONITORING, INSPECTION AND REGULATION AT BOTH UTILITY AND NATIONAL LEVEL,

THE NECESSARY APPARATUS IS NOT YET IN PLACE. BUT I CAN SAY THAT

ON THE BASIS OF THE EXCHANGES WE HAVE HAD WITH THE CHINESE

AUTHORITIES SO FAR, THE STEPS THEY HAVE TAKEN AND THE ANNOUNCEMENTS THEY HAVE MADE, WE ARE CONTENT THAT THE PROJECT

SHOULD GO AHEAD.

ENDS

YOUNG

OCMIAN 8961

GUANGDONG

[COPIES SENT TO NO 10 DOWNING STREET]

ADDITIONAL DISTRIBUTION

GUANGDONG NUCLEAR

PS

LIMITED

HKD

FED

NED

TRED

PUSD(MR CROWLEY) WED

PS/MR RENTON PS/PUS

SIR W HARDING

MR DAUNT

MR WILSON MR SLATER

3

CONFIDENTIAL