MAKE USE OF THE REPORTING SYSTEM ALREADY
ESTABLISHED FOR THE PROJECT.
DURING THE INITIAL PHASE OF THE CONTRACT,
WHEN THE CRITICAL MANUFACTURING OPERATIONS
ARE TO TAKE PLACE, THE DEPARTMENT WILL
RECEIVE TECHNICAL REPORTS FROM GEC ON DESIGN
AND MANUFACTURING PROGRESS.
THE DEPARTMENT WOULD BE READY TO ATTEND
THE MORE IMPORTANT PROGRESS REVIEW
MEETINGS. THE DEPARTMENT UNDERSTANDS
THAT INITIALLY THESE WOULD NORMALLY
TAKE PLACE IN THE UK OR FRANCE.
DETAILED DISCUSSIONS WILL AGAIN BE
REQUIRED TO ESTABLISH AT WHICH MEETINGS
THE DEPARTMENT SHOULD BE REPRESENTED.
IV
IN ACCORDANCE WITH GEC'S CONTRACTUAL
RESPONSIBILITIES, THE DEPARTMENT WOULD
EXPECT ITS MONITORING ACTIVITY TO
REDUCE FOLLOWING DELIVERY OF EQUIPMENT
BY GEC. HOWEVER THE DEPARTMENT WOULD
PROPOSE TO MAINTAIN ITS MONITORING TEAM
UNTIL PROVISIONAL ACCEPTANCE OF THE
SECOND UNIT, AT WHICH TIME IT WOULD
REVIEW WITH THE CLIENT THE NEED FOR
CONTINUED MONITORING DURING THE
THE ABOVE ARRANGEMENTS ARE DESIGNED TO ENSURE
THAT THE DEPARTMENT IS FULLY AWARE OF THE
PROGRESS MADE ON THE PROJECT AND THE EXTENT TO
WHICH UK COMPANIES ARE MEETING THEIR CONTRACTUAL
OBLIGATIONS. SHOULD THE DEPARTMENT BECOME AWARE,
THROUGH THE REPORTS IT RECEIVES OR APPROACHES
FROM THE CLIENT, THAT THE PERFORMANCE OF UK
COMPANIES IS GIVING SERIOUS CAUSE FOR CONCERN,