ROADS (WORKS, USE AND COMPENSATION) ORDIHATICE (Chapter 570)

Scheme annexed to Plan Hos. TWCE/828A and TWOR/829 describing

Intersection of Castle Peak Road and Kwai Chung Roada,

Improvement Stage 11

General Description of the Works

The proposed works, as shown on Plan No. TWCE/828A, comprise the

construction of a three level interchange at the intersection of Crable Penk

Road and Kwai Chung Road. This will include two 2-lane flyovers, one rumiar

north-south on the line of Kwai Chung Road and Cheung Wing Road, and one

running cast-west of the line of Castle Peak Rond. Al ground level Castle

Peak Road, Kwai Chung Road and Cheung Wing Rond will all be widened, and a

footbridge system will be built at the junction incorporating an elevated

walkway on the west side of Kwai Chung Read. A new subway under Carlle Took

Rond will also be built commecting to in Win; Jane.

2.

On completion the works will improve both vehicular and pedestrian

flows at the interchange whilst enhancing safety.

Land Resumption

3.

The land which the Secretary for Lands and Works proposes to be

resumed under Section 13 of the Roads (Works, Use and Compensation) Ordinance

(Chapter 370) is shown on Plan No. TWCE/829.

Roads to be closed or modified

1.

A section of the existing; Kwong Fai Cireni! shown hatched in red

on Drawing No. TWCK/828A will need to be closed permanently under section 17.

Alternative access will be provided by the new roadworks, as shown coloured

brown on the same plan, prior to the road closure.