CD488 5/76
VOLUME 8
REON. NO:
O.D.M.
ACCEPTANCE
No.
(ANNEX 20)
Appendix 1 to ANNEX 1 (OP IIIB-9)
(paragraph 4c ANNEX 1)
CONTRACT CERTIFICATE
{FOR CHEMICALS AND ALLIED PRODUCTS USE ALTERNATIVE ‘CERTIFICATE' OVERLEAF)
PARTICULARS OF CONTRACT
1. Date of Contract.
2. Contract No.
3. Description of goods or services to be supplied to the purchaser...
If a number of items are to be supplied, a detailed list should be appended to this certificate.
4. Total contract price payable by purchaser (state CIF, C&F or FOB) £..
IF GOODS ARE TO BE SUPPLIED THE FOLLOWING SECTIONS MUST BE COMPLETED. If the contractor is exporting agent only, the information requested should be obtained from manufacturer.
5. Estimated % of the FOB value of the goods not originating in the United Kingdom, but purchased by the contractor directly
from abroad, i.e. % of imported raw material or components used to manufacture.
(a) % FOB value...
(b) Description of items and brief specifications
6. If any raw material or components used originated from abroad, e.g. copper, asbestos, cotton, wood pulp, etc., but have
been purchased in the United Kingdom by the contractor for this contract, specify:-
(a) % FOB value
(b) Description of items and brief specifications.
IF SERVICES ARE TO BE SUPPLIED, THE FOLLOWING SECTION SHOULD ALSO BE COMPLETED
7. State the estimated value of any work to be done or services performed in the purchaser's country by:-
(a) Your firm (site engineer's charges, etc.)
(b) Local contractor.
8. Qualifying remarks as necessary in respect of paragraph 5, 6 or 7 above
9. I hereby declare that I am employed in the United Kingdom by the Contractor named below and have the authority to sign this certificate. I hereby undertake that in performance of the contract no goods or services which are not of United Kingdom origin will be supplied by the Contractor other than those specified in paragraphs 5, 6, 7 and 8 above.
Note: For the purpose of this declaration the United Kingdom
includes the Channel Islands and the Isle of Man.
CONTRACTORS SHOULD NOTE THAT GOODS
SHOULD NOT BE MANUFACTURED UNTIL
ACCEPTANCE HAS BEEN NOTIFIED
FOR OFFICIAL USE ONLY
Name or number of Project
Amount Committed
£
Acceptance
Date of Entry
Date
Initials
Signed...
Position held.
Name and Address of Contractor..
Date..
PAYMENTS
Date
Amount
PA No.
Initials
September 1980
.1...
OP Vol III Amendment No 503
131
November 1979
AL/2