LANDS DIVISION
密
Subject
Major Development Studies
(a) N. Lantau
(LW(SPU)70/61/01)
CONFIDENTIAL
Purpose
LANDS AND WORKS BRANCH PROGRESS REPORT
1st November 1981 to 31st January 1982
To make a comprehensive study of the development potential of various sub-regions in Hong Kong to provide the basic information on a comparable basis for the selection of a preferred development strategy.
Part I
Progress Made & Present Position
Next Quarter Targets
(a) N. Lantau
(a) N. Lantau
機密
CONFIDENTIAL
(i) The steering group established
to guide the further develop- ment of conceptual planning proposals and detailed engin- eering studies continued with its work programme.
(ii) Consultancy study on the
replacement airport at Chek Lap Kok continuing.
(iii) Detailed design of the
Lantau Fixed Crossing being carried out by consultants.
(i) Monitor
Progress of the further studies
(completion September 1982).
(ii) Monitor
pro oss in studies relating to CLK replace- ment airport.
(iii) Monitor
progress in detailed design of
the Lantau Fixed
Crossing.
GF 323
CONFIDENTIAL
機密