LANDS AND WORKS BRANCH PROGRESS REPORT

1st February 1982 to 30th April 1982

Subject

a) N. Lantau

(LW(3PU)70/61/10)

Purpose

basis for the selection of a preferred develop- ment strategy.

Progress Made & Present Position

Next Quarter Targets

(a) N. Lantau

(i) The steering group

established to guide the further development of

conceptual planning pro-

posals and detailed engineering studies con- tinued with its work

programme.

(ii) Consultancy study on the

replacement airport at Chek Lap Kok continuing. General feasibility studies have been completed and more detailed civil

engineering, environmental, financial, meteorological and master plan studies are proceeding.

(iii)Detailed design of the

Lantau Fixed Crossing being carried out by

consultants.

(b

N.W. New Territories

(Sru) 70/61/03)

(b) N.. New Territories

(i)

Consultants commenced work on a base strategy to

(a) N. Lantau

(i)

Monitor

Progress of the further studies (completion September 1982).

(ii) Monitor pro-

gress in studies relating to CLK

replacement airport.

(iii)Monitor pro-

gress in detailed

design of the Lantau Fixed

Crossing.

(b) N.w. New

Territories

(i) Consultants

CONFIDENTIAL ##