Progress made and present position
Next quarter
target
16. Secondary School
Expansion
Programme
To
ensure that the approved secondary schools building programme proceeds on schedule.
The Schools Building Review Committee met on 7 July 1982 and the Schools Building Programme is being revised to take account of progress on school development. Discussion had been held with HD, NTDD and ED and it was agreed that the existing procedures should continue. It was also agreed that in formalising any new stage of School Building Programme the relevant departments including Project Managers and Principal Government Architect should be
involved to ensure that а realistic target date of completion
was established.
To continue to
monitor the school building
programme.