CONSTRUCTION COSTS

commitment of Hong Kong resources required to im- plement a replacement airport programme. In 1979 Hong Kong dollars, this commitment would be about HK $9.6 thousand million, excluding credits for salvage of land and facilities now used for other purposes.

38

The Consultants have developed cost estimates for constructing the replacement airport based on prices prevailing as of mid-1979. All costs are expressed in Hong Kong dollars, and the detailed report provides the basis for developing unit cost estimates for each line item. The costs summarized below are divided into three discrete phases:

Phase la is the initial runway, taxiway, and all related support facilities.

Phase Ib is the additional fill south of the

immediate environs of the airport in Tung Chung Bay.

Phase II is the second runway, taxiway system and related support facilities.

Costs have been subdivided into those that traditionally accrue to the airport account and those that are normally the responsibility of tenants or the Government. These cost elements have been totalled to indicate the full

RMP PARSONS OVERSEAS COMPANY •WOK kaotle

HK$ (million)

Task

Airport Account

a

Tenants

Total

Phase Ia

Single-runway airport

5,508

1,539

7,047

Phase Ib

Tung Chung

Bay adjacent to

airport

269

269

Phase II

Two-runway

airport

1,749

578

2,327

Grand Total

7,257

2,386

9,643

a

Tenants include government facilities not directly related to airport operations.