CONSTRUCTION COSTS
commitment of Hong Kong resources required to im- plement a replacement airport programme. In 1979 Hong Kong dollars, this commitment would be about HK $9.6 thousand million, excluding credits for salvage of land and facilities now used for other purposes.
38
The Consultants have developed cost estimates for constructing the replacement airport based on prices prevailing as of mid-1979. All costs are expressed in Hong Kong dollars, and the detailed report provides the basis for developing unit cost estimates for each line item. The costs summarized below are divided into three discrete phases:
Phase la is the initial runway, taxiway, and all related support facilities.
Phase Ib is the additional fill south of the
immediate environs of the airport in Tung Chung Bay.
Phase II is the second runway, taxiway system and related support facilities.
Costs have been subdivided into those that traditionally accrue to the airport account and those that are normally the responsibility of tenants or the Government. These cost elements have been totalled to indicate the full
RMP PARSONS OVERSEAS COMPANY •WOK kaotle
HK$ (million)
Task
Airport Account
a
Tenants
Total
Phase Ia
Single-runway airport
5,508
1,539
7,047
Phase Ib
Tung Chung
Bay adjacent to
airport
269
269
Phase II
Two-runway
airport
1,749
578
2,327
Grand Total
7,257
2,386
9,643
a
Tenants include government facilities not directly related to airport operations.