PART I

NEW TERRITORIES ADMINISTRATION

QUARTERLY PROGRESS REPORT

(1st NOVEMBER 1980 - 31st JANUARY 1981)

SUBJECT

PURPOSE

Land Disposal

To make land available for development

CONFIDENTIAL

No Lantau

De eopment

To investigate develop- ment potential in North Lantau and to co- ordinate departmental efforts on the proposed resiting of the airport to Chap Lap Kok and the proposed fixed crossing linking lantau within the mainland.

PROGRESS MADE & PRESENT POSITION

1. PUBLIC AUCTION : sites were disposed of

totalling 16594 m in all; of these 2 were industrial, one was residential, one was commercial/residential & the remaining site was designated for non-industrial/ hotel use. By district 2 sites were located in each of Sha Tin & Sai Kung and one site in Tai Po.

2. LETTER A/B 1ENDER: 9 sites were disposed

of totalling 267799m in all. These comprised 7 non-industrial sites and 2 industrial sites. By district 5 were located in Sha Tin and 4 in Yuen Long.

3. PUBLIC TENDER: 2 petrol filling station

sites in Sha Tin were tendered.

Appointment of consultants for detailed engineering design being finalised.

NEXT QUARTER TARGET

1. PUBLIC AUCTION : 6 lots are to

be offered for sale totalling 33406m in all. Of these 5 are residential sites and one industrial/godown. By district 3 sites are located in Sha Tin, one in Sai Kung and 2 in Islands.

2. LETTER A/B TENDER: 15 lots arel be offered totalling 84972m in all.

Of these 5 are residential sites, 6 are non-industrial sites and 4 are designated industrial/ godown. By district

located in Sha Tin, 4 in Yuen Lon and 1 in Tai Po.

3. OTHERS: One site of

2400m2 in

Tin is scheduled to be let to Hong Kong Telephone Co Ltd.

CONFIDENTIAL

Preparatory work on land clearance for detailed engineering studies in hand. Consultants for detailed engineering studies & Master Layout Plan for Chap Lap Kok to be appointed.