Operational aspects. including power despatch,
power control, protection and telecommunication were being studied.
Budgetary unit prices for transmission equipment were being acquired for evaluation of transmission costs.
DISCUSSION WITH NUCLEAR REACTOR VENDORS
29.
make arrangement
for
Mr. Stones was asked by Mr.
by Mr. Chen discussions with nuclear reactor vendors. These discussions would be held in Guangzhou and would be attended jointly by KEC and CLP. Mr. Stones would prepare a schedule for consideration by KEC.
NEXT MEETING
30.
The next Management Group Meeting would be held on 9th July, 1980 in Guangzhou.
ybl:sl
2nd July, 1980