MANAGEMENT

26.

12

On management of the nuclear power station, Mr. Stones stated that he agreed with the idea of joint management in accordance with equity shares. He stressed that it was. important to allocate the appropriate person to the right position and responsibility.

POWER STATION SITE

27.

Mr. Stones reported that a visit to the site at Dong Shan Wan had been made on 13th June, 1980. The site was found satisfactory and was enviromentally less sensitive to the population in Hong Kong and Shum Chun. Site investigations were being carried out.

SYSTEM DESIGN

28. Dr. Lee reported the progress and findings made by the System

Design Subcommittee :

(a)

(b)

(c)

Frequency response studies of the Guangdong/Hong Kong power system showed that the maximum generating unit capacity

could be accommodated interconnected system was 900 MW.

which

by

the

The maximum station capacity which could be accommodated by the interconnected system was 2x900 MW.

were being

transmission

the

nuclear power

Alternative transmission configurations evaluated. to identify the optimum

for accommodation of arrangement

station. Loadflow, security assessment, short circuit level, transient and steady-state stability studies were being carried out.

Cont'd