ANNEX B
Projects in the Reprovisioning of R.A.F. Kai Tak
(b)
Project
1
(c)
: Completion
dates of
projects on schedule
(d)
Completion dates of delayed projects
KT 1
KT 2
Construction of 121 quarters at Sek Kong Village for married airmen
Construction of 20 quarters at Sek Kong Village for married officers
See Note (1)
7 April 1978
KT 3
An addition to the sergeants mess at Sek Kong North Camp
September 1977 (refurbishment
January 1978)
KT 4
Construction of a helicopter hangar at Sek Kong North Camp
8 March 1978 (2)
KT 5
Construction of an administration
16 March 1978
and supply building at Sek Kong North Camp
KT 6
Construction of a bulk fuel
16 April 1978
KT 7
storage facility at Sek Kong North Camp
Construction of a fuel bowser repair bay at Sek Kong North Camp
22 March 1978
KT 8
Refurbishment of barrack blocks at Sek Kong North Camp
November 1977
KT 9
Extension of the Medical Centre at Sek Kong North Camp
22 March 1978
KT 10
Extension of the amenities and recreational facilities in Sek Kong Village
August 1978
KT 11
Construction of a sports pavilion at Sek Kong North Camp
January 1978
KT 12
Extension of the arms store in Sek Kong North Camp
28 February 1978
KT 13
Minor improvements to the officers January 1978 mess at Sek Kong North Camp
KT 14
Improvements to the NAAFI at Sek Kong North Camp
February 1978
KT 15
20 February 1978
Construction of a Services Postal Unit at Osborn Barracks, Kowloon