ANNEX B

Projects in the Reprovisioning of R.A.F. Kai Tak

(b)

Project

1

(c)

: Completion

dates of

projects on schedule

(d)

Completion dates of delayed projects

KT 1

KT 2

Construction of 121 quarters at Sek Kong Village for married airmen

Construction of 20 quarters at Sek Kong Village for married officers

See Note (1)

7 April 1978

KT 3

An addition to the sergeants mess at Sek Kong North Camp

September 1977 (refurbishment

January 1978)

KT 4

Construction of a helicopter hangar at Sek Kong North Camp

8 March 1978 (2)

KT 5

Construction of an administration

16 March 1978

and supply building at Sek Kong North Camp

KT 6

Construction of a bulk fuel

16 April 1978

KT 7

storage facility at Sek Kong North Camp

Construction of a fuel bowser repair bay at Sek Kong North Camp

22 March 1978

KT 8

Refurbishment of barrack blocks at Sek Kong North Camp

November 1977

KT 9

Extension of the Medical Centre at Sek Kong North Camp

22 March 1978

KT 10

Extension of the amenities and recreational facilities in Sek Kong Village

August 1978

KT 11

Construction of a sports pavilion at Sek Kong North Camp

January 1978

KT 12

Extension of the arms store in Sek Kong North Camp

28 February 1978

KT 13

Minor improvements to the officers January 1978 mess at Sek Kong North Camp

KT 14

Improvements to the NAAFI at Sek Kong North Camp

February 1978

KT 15

20 February 1978

Construction of a Services Postal Unit at Osborn Barracks, Kowloon