MAY FIND HELPFUL IN THIS CONTEXT®-
AA2 PLEASE REFER TO VOLUME 4 SECTION 1 OF TENDER MEMORANDUM AND SECTION 4 WHERE PROVISIONAL SUMS ARE DISCUSSED. SEE IN PARTICULAR SECTION 3 PARA 2.0 AND PARA 4.0 FOR REASONS GIVEN IN THE TEXT NOT POSSIBLE UNTIL SURVEYS, SOIL INVESTIGATIONS, TOWER POSITIONS AND ROUTES COMPLETED, TO BE MORE PRECISE ON EXACT COSTS. PROVISIONAL SUM IS THEREFORE GIVEN AS SHOWN IN VOL 1 SECT 4. THE FULL LIST
IS AS FOLLOWS
CROSSOVER OF 400/132 KV (ONE ONLY)
LINES BETWEEN POWER STATION AND TERMINAL TOWERS AS YET UNDEFINED BUT POSSIBLE REQUIRING SPECIAL TOWERS OR GANTRIES
-EXTRA STEELWORK FOR TOWER EXTENSIONS
ADDITIONAL FOUNDATION WORK, INCLUDING NON-NORMAL TYPE FOUNDATIONS, ROCK EXCAVATIONS, DRAINAGE CHANNELS,
TIMBERING AND PUMPING
ADDITIONAL EARTHING REQUIRED TO ACHIEVE RESISTANCE MAKING GOOD EXISTING ROADS DAMAGED BY CONSTRUCTION ACTIVITIES AND STRENGTHENING BRIDGES AND CULVERTS LANDSCAPING TOWER SITES AND PLANTING SHRUBS
PAINTING TOWERS
SOIL INVESTIGATION AT TOWER SITES
CASTLE PEAK POWER STATION CONNECTIONS
CC4 FOR BASIS OF CIVIL ENGINEERING DESIGN SEE VOL 2 PARA 2.2.6
E E FOR DESCRIPTION OF PROJECT MANAGEMENT ORGANISATION SEE
VOL 1 SECTION 6
DD1 SPARES. PLEASE REFER TO VOL 1 SECTION 2.2.2. FOR GENERAL
COMMENTS. THE PROVISIONAL SUM COVERS ALL SPARES
GS1 PLEASE REFER TO VOLUME 1 SECTION 2.1.2 FOR PROVISIONAL
SUM AND VOLUME 2 SECTION 2 FOR SCOPE OF WORK
KK PLEASE REFER TO VOLUME 1 SECTION 2.1.9 WHERE WE OFFER TO INVOICE AT COST OCEAN FREIGHT AND INSURANCE. IN SAME SECTION WE OFFER LIKEWISE TO CHARGE AT COST THE DELIVERY
FROM CIF HONG KONG TO SITE.
LL
PLEASE REFER TO VOL 1 SECTION 7. B3 CONDITIONS OF CONTRACT CLAUSES 22 AND 24 AS AMENDED IN SECTION 7.