PLANNED PROCUREMENT PROGRAMME

1.

*2.

*3.

4.

*5.

*6*

7.

8.

9.

Complete NST studies

Forward study reports to CBFHK

Draft Naval Staff Requirement (NSR)

NSR to Naval Projects Committee MOD

Invite design and building tenders

Select design and shipbuilders

Place order

Accept vessel 01

Accept final vessel

Early May 78

Mid May 78

June Nov 78

www

Dec 78

Autumn 79

Feb/Mar 80

May 80

Mid 82

End 83