密
SUBJECT
PURPOSE
ENVIRONMENT BRANCH PROGRESS REPORT
1ST AUGUST 1976 TO 31ST OCTOBER 1976
PART II
IMPORTANT ISSUES
PROGRESS MADE & PRESENT POSITION
NEXT QUARTER TARGETS
34. Central
District
Development Programme
(ENV 10/3151/
68)
To provide a phased programme For major development projects in the Central District Outline! Zoning Plan area and monitor their implementation. ALL major projects to be completed by 1985.
(a) Major development projects have
been identified and tentative land use proposals for the Western Reclamations have been
agreed.
(b) Land use proposals for the
Central Reclamation Stage V have still to be agreed.
(a) Complete draft
Development Programme.
(b) Prepare submis-
sions for the next meeting P.W.P.C.
CONFIDENTIAL