CONFIDENTIAL #
*
PART II
Important Issues
SUBJECT
(EPCOM cont' .....)
LAND DEVELOPMENT
Macau Ferry Terminal Redevelopment
(ENV 70/03/01)
PURPOSE
(b) To advise the S. for E.
measures to combat pollution.
on
To conclude negotiations with the developer of the new terminal facilities and obtain approval to the conditions of grant by the end of April 1977.
PROGRESS MADE & PRESENT POSITION
(b) A special meeting was held on
20.12.76 between Dr. Bidwell of the Environmental Resources Limited (E.R.L.) and the Chairman and Sub- Committee Chairman of EPCOM to dis- cuss the timing regarding the completion of the E.R.L. study and their consultation documents and drafting instructions.
NEXT QUARTER TARGETS
(b) A special meeting
will be arranged in late February for the Chairman and Su Committee Chairman of EPCOM to meet the E.R.L. consultants again to discuss the drafting of the final reports.
) An estimate is still awaited from
the developer of the cost of the terminal building so that the area of land of equivalent value which is to be granted to the developer may be calculated.
(b) A Working Party under the chairman-
ship of the Principal Government Land Agent met for the first time
(a)(i) Receive estimate
of cost from the developer;
(ii) complete survey
of land to be granted to dev- eloper in exchange;
CONFIDENTIAL
(iii) draft conditions
of grant.
(b)(i) Agree with
terminal operators the Working
G.F. 323