G.F. 323

CONFIDENTIAL ** 機密

Tublic Relations

24.

Anything to do with the Walled City is big news.

It is

therefore important for Government to work out in advance answers to all

With a good question and answer

those questions that one can anticipate.

brief all departments involved in the exercise can speak with one voice.

Preferably, there should be only one Government spokesman.

Since

Government's position is weak, in that it has left these buildings

undetected for so long, it is recommended that a defensive line similar

to the one adopted in the 1975 operation be taken. A significant factor

will also be the phasing of action.

Programme of Action

25.

If action is to be taken, it is recommended that a phased

The timing for each stage will have to be

programme be initiated.

carefully considered in the light of both internal and external factors.

The first stage should be a pilot project aimed firstly at testing the

temperature, and secondly to establish a pattern which could be followed

for latter stages. It is suggested that for Stage I of the programme,

only one building be tackled. This building was selected after a site

visit by D.S. for S. and agreed by D.C.A. It is 36-38 West City Road

i.e. Building E in Appendix I.

26.

into account:

In choosing this building the following factors were taken

(a) height in excess of the flight path 28 ft. 6 in.;

(b) accessibility - it is situated on the periphery of

the Walled City with relatively little problem of

access;

(c) number of flats involved 3 storeys consisting of

-

6 flats would have to be demolished. This will give

departments concerned ample opportunity to test the

acceptability of the compensation scheme and the

adequacy or otherwise of the solutions to the various

anticipated problems. A rough operational outline

CONFIDENTIAL

Tactical..

Page 105Page 106