Plant Requirements

8

The effect of the higher demand pattern on CLP's plant requirements has been to bring forward their expansion of capacity approximately one year. They consequently propose to commission:

(a) the planned 100 mw gas turbine in 1980 instead of

in 1981;

an additional 200 mw of gas turbine capacity in 1981;

(b)

(c)

the 1st and 2nd 350 raw sets in 1982 and 1983 as originally planned; and

(d)

the 3rd and 4th 350 mw sets one year early, in 1984 and 1986 respectively, provided demand develops as forecast.

The revised expansion programme is set out below (c. f. paragraph 8 of Annex A to XCC(77)86).

Table II

Financial

Year

Maximum Demand

MW

Capacity Added

MW

Capacity Capacity

Retired

MW

Capacity/

Installed

Max Demand

MW

%

1977

1,380

Y4 200

2, 212

160

1978

1, 490

A1/2/4-60

2, 152

144

1979

1, 625

2, 152

132

1980

1, 785

GT 100

2,252

126

1981

1, 940

GT 200

2, 452

126

1982

2, 105

L1 350

2,802

133

1983

2,280

L2 350

1

3, 152

138

1984

2, 465

L3 350

1

3,502

142

1985

2,660

-

3.502

132

1986

2,860

L4 350

3,852

135

1987

3,075

U1 500

4,352

142

А

YGLUA

=

GT

=

# #

=

oil fired (already installed)

gas turbine

dual fired (coal and oil)

to be decided

oil fired (at Hok Yuen)