HONG KONG PROJECT

:

Possible progress of energy development programme.

1

Site selection and evaluation

2

3

Determination of totality of items of hardware to be covered by UK proposals

Preparation of detailed proposals for the supply of specific items of hardware as detailed in Para 2 above

Evaluation of proposals in UK

4

(a)

5

6

as to technical matters (b) as to price

Submission of proposals and financial arrangements to CLP

Negotiation of contracts and Financial Agreements

7

Signature of contracts and Financial Agreements

8

9

10

Inspection and testing of work in progress (in UK)

Erection in Hong Kong

Supervision of Erection

CLP (with CEGB assistance)

CEGB & CLP

UK companies as determined by Dol

CEG B

DOI

DOI

CLP with UK

companies co-ordinated by DoI. CEG B

available to assist

on technical matters.

CLP & individual UK companies

CEG B

11

Training and appointment of skilled people

Commissioning of plant

12

13

Running of plant

CLP

UK companies with quality control surveillance by CEGB

CLP & CEGB

UK companies with assistance of CEGB and CLP

CLP & if required CEGB