G.F. 323

機密

CONFIDENTIAL **

NOTE BY THE PUBLIC WORKS

DEPARTMENT

Technical Data

Immersed tube

tunnel

2400 m

ANNEX C

Bored tunnel

3600 m

Length including

approaches Depth of tunnel

Gradient

87 m below P.D.

55 m below P.D.

5%

5%

Carriageway

2 lanes

Estimated Cost

Immersed tube

tunnel (million)

2 lanes

Bored tunnel

(million)

430

Tunnel

Approaches

Contingency 25%

Total

513

45

45

558

475

140

120

698

say 700 million

595

say 600 million

2.

(excluding investigation and

consultant fees and land cost)

The estimated cost of the immersed tube tunnel is based upon the figure given in Wilbur Smith's interim report on Lantau Fixed Crossing adjusted for length, cross-section and difficult sea-bed conditions. In the case of the bored tunnel the cost is estimated on the tender price of Aberdeen Tunnel.

3.

Immersed tube tunnel

The tunnel has to descend to a depth of 55 m below P.D. to clear off the shipping channel in Kap Shui Mun and to climb to +60 m to join Tuen Mun Road. Because of the deep depression at the sea-bed it would be necessary to build the tunnel along the slope of the seabed.

CONFIDENTIAL

/4.

機密