TO IMMEDIATE D T I TELNO CREDA 96 OF 29 JUNE.

FOR MACDONALD 1C2.

POWER STATION PROJECT,

MY TEL CREDA 95.

RECEIVED IN RAMSERY NO. 51

3 CJUN1977

TOKK 164)1

GUIDELINES PROMISED BY CLP LEFT HERE BY BAG TODAY. THE BULKY DOCUMENT CONTAINS PRELIMINARY SPECIFICATIONS FOR THE PLANT (TYPE, RATING, OPERATING CONDITIONS, SITE CONDITIONS AND DESIGN CONSIDERATIONS), BOILER, TURBINE, GENERATOR AND EXCITER, LUBRICATING, COOLING AND CONTROL SYSTEMS, ELECTRICAL SYSTEMS, SUPPLEMENTARY EQUIPMENT (1.E. HYDROCLORINATION, HYDROGENERATION, WATER TREATMENT, FIRE PROTECTION, AIR-CONDITIONING ETC.) AND THE

GAS TURBINES.

2. IN COVERING LETTER STONES REFERS TO PROBABLE SITE OF NEW STATION

ON NORTH-EAST COAST OF LANTAU. TWO TWELVE FOOT DIAMETER TUNNELS

WILL BE NEEDED TO CONVEY EHV POWER CABLES TO THE MAINLAND AND

PROVIDE POSSIBLE ACCESS FOR PERSONNEL DURING EMERGENCY CONDITIONS.

CLP EXPECT THE UK GOVERNMENT PACKAGE FOR THE POWER STATION TO

INCLUDE COST FOR SUCH TUNNELS AND EHV CABLES FROM THE STATION TO

A POINT ON THE MAINLAND WERE IT CAN BE CONNECTED INTO A NEW CLP

EHV TRANSMISSION SYSTEM.