0003160 G.F. 316

SECRET

!

9。

(a)

- 7.

seeks to maximize usage and,

therefore, revenue; and

(b) will afford the maximum relief

of traffic congestion.

Now that the Modified Initial

System has been approved, the Provisional

Authority will shortly announce the terms

and conditions by which interested parties

may tender for parts of the project, the

Government having decided that the project

should now be proceeded with on a multi-

contract basis. Work is now proceeding

on the preparation of tender documents.

It is hoped that contracts can be let

within the next six months and that

construction can start immediately

thereafter. The aim is to complete

construction of the Modified Initial

System to have it fully operational

by mid-1980.

10.

The Provisional Authority

regrets its inability to make an earlier

statement on the position regarding this

important project. This has been partly

because it was in the process of

developing a Modified Initial System

SECRET