à revision of the price ceiling from

$5 billion to $6 billion together with

provision for price escalation.

3.

The Provisional Authority could

not accept this request. It holds the

view that the Consortium should have

been able to assess the effects of the

oil crisis on Japan's economy during the

period between the Hong Kong Government's

acceptance of its pre-emptive bid (11th

December 1973) and the time it signed

a Letter of Intent (15th February 1974).

The Provisional Authority therefore

considers that the Consortium has

committed a serious error of judgement

which will result in Hong Kong suffering

at least a year's delay in building the

Mass Transit Railway with all the

attendant consequences.

The Provisional

Authority holds the view that Hong Kong

should not have to suffer from this

error of judgement and it accordingly

lodged a claim for compensation with

the Consortium. At a meeting held on

9th January the Consortium refused to pay

compensation, but offered a nominal ex

gratia payment of ¥300 million