APPENDIX IX

PROGRESS CHART OF A GOVERNMENT SECONDARY SCHOOL PROJECT UNDER NORMAL CONDITIONS (Assuming that site formation and building can be done under one contract)

Entered in Category C

Allocation of Site

5

10

15

1

2-

20

25

2-

30

35

40

Entered in Category B

Preparation of Sketch Plans and

Schedule of Accommodation

Submission and Approval of Estimates

Entered in Category A

Structural and Detailed Drawings

Bills of Quantities and Tender

Documents

Tendering Period

Supplementary vote procedure

Construction Period

Provision of Furniture/Equipment

L

AVERAGE TIME FOR COMPLETION OF PROJECT (46 months)

months