APPENDIX VIII
PROGRESS CHART OF AN AIDED SECONDARY SCHOOL PROJECT UNDER NORMAL CONDITIONS (Assuming that site formation and building can be done under one contract)
0
10
15
2-0
22-5
30
35
40
months 45
1
Processing of Application by E.D.
Recommendation to C.S.
Processing of Basic Terms for Grant
of Site
Executive of Lease Conditions
Processing of Sketch Plans by E.D.
Approval from Fire Services and
other Departments
Preparation of General Building
Plans by Architect
Approval of General Plans by B.O.O.
Preparation of Structural Plans and
Architectural Details
Approval of Structural Plans by
B.O.O.
Preparation of Bills of Quantities
by Q.S.
Approval of Drainage Plans and
Plumbing Plans etc.
Approval of Tender Documents and
List of Tenderers
Tendering Period
Reports/Recommendation on tenders
by sponsors and professional advisers Application for Refinancing
Construction Period
Ordering of Furniture/Equipment
E E E
E E
E
E
AVERAGE TIME FOR COMPLETION OF PROJECT (46 months)