Thursday, February 26, 1970.

FIRST MAJOR CONTRACT FOR KAI TAK EXTENSION

Expected To Be Lot By End Of July

The first major contract for extension of the runway promontory

at Kai Tak by about 2,530 feet should be let by the end of July, with

work beginning soon afterwards to enable completion of the whole project

in 1973.

The $115 million extension --one of the biggest projects in

the Public Works programe --is designed by Scott Wilson Kirkpatrick

and Partners, consulting civil engineers, who will also supervise its

construction.

The new runway will have an overall length of 11,130 feet.

At its narrowest section, the overall width of the reclamation at the

top of the seawalls will be 830 feet, comprising the runway proper -

a centre strip 200 feet wide and grass strips, 250 feet and 260

feet wide, to the west and east of the runway proper, and a 75-foot-

wide taxiway with an adjacent 45-foot-wide surfaced strip to the crest

of the east seawall.

Towards the seaward end of the new runway, there will be

a by-pass area, and next to it a subsidiary fire station.

/The reclamation.