11 | 12

12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48

Order and await berth No. 1 cranes (2 No.)

15

Erect and commission berth No.1 cranes

+22

MONTHS

2

4

5

6

7

8 9 10 11

PHASE I

Authorisation of reclamation

Start surfacing and buildings

12

Key:-

Continue

surfacing

124

Start

event

End event

Activity

2/2

Years

(the duration of each activity is indicated

in months)

Finish main

Finish main

Finish drive

seawoll dredge

seawall

sand

concrete

plies

Finish maln

seawall rubble

--- TEE

107

Start

Start

main

seowoll

'stawa}) }

dredge

sand

Start "drive concrete piles

Start main seawall

rubble mound

Start main

seawall

Finish main seawalli

Finish reclamation

Finish surfacing and open berth Noll,

101

103

108

119

123

(25)

126

Finish return seawall

dredge

Start retur isand)

105

Start return

seawall rubble

2

Start

return

Seawall

Finish return seowoll

[109

13

Start precost

piles

102

3

Finish

return

06 and

Finish

1

Finish

return

110 Cubble

Pre-reclamation

dredging

precast Start precasting

piles

decking

1

[12

Dredge

berth No. approaches

Design and let contract

7

001

003

PHASE 2

MONTHS

2 3 4

ENGINEERING REPORT

CONTAINER TERMINAL

KWAI CHUNG

On

5 6

7

8

Finish precasting

decking members

117

Start reclamation

120)

120

Start

decking

Finish

118

decking

3

Dredge barth No. 2 approaches

Dummy (logical link or constraint not representing

a specific operation)

Spare time (float) available for an activity

Time to key event

Critical path to key event (heavy line)

Notes:-

I.

Direction of arrows indicates sequence.

2. (1) [101] LO 126

are Phose | events.

Continue front

27

reclamation

3

221

Finish front

reclamation

3

3 Years

Finish surface

224

(1)

[201] to [227

ore Phose 2 events.

3

(1)

(001) to 003) are common to both phoses.

Order and await

Sheet piles

Start sheet piling

Finish sheet piles

Finish dredge

cells

Finish drive concrete

piles

„Pinish fill cell

₤202

(20

209

215

216

7

Start dredge

cells

Stort

Stort drive concrete piles

celis

208

201

214

Start precasting piles,

Finish precosting piles

201

-203

Stort

crone beans

218

Finish crane

beams

Surface cells and open berth No. 2

223

225

3.

To be read in conjunction with Drawing 16.

4. Activities (003) to [219] and 219 to 225,

only included if odditional cranes required -- para. 15.6 (†) reters.

32

Years

Reclamation behind breakwater

Sand drains

Consolidation

Surfacing and behind existing

buildings breakwater

Complete and clear sits

206

213

222

226

221

12

Pre-rectomation

dredging

Start front

reclamation

Excavote in existing breakwater

204

6

Stort surfacing and packing shed

5

[212

Continue surfacing and finish pocking shed

2

Access flyover

18

Order and awalt berth No. 2 cranes (2 No.)

15

* See note 4

Erect and commission berth No.2 cranes

(219 Jun

7

9 10 11 12 13 14 15 16 17 18 19 20 21 | 22 | 23 | 24 | 25 | 26 | 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48

PROGRAMME

NETWORK

FOR

STAGE

I

PORT WORKS DIVISION

P. W. D. HONG KONG

20

Share This Page