Contractors
Main contractor for the school and church was Shun Hing Co. Air condi- tioning was installed by British General Electric Co. Ltd.
Sub-contractors included:
Otis Elevator Co.-lifts Armstrong Cork Co.—
ceiling tiles
Duro Industries Ltd.-
vermiculite acoustic ceilings
Mobil Oil Co.-paint Petman Ltd.-alumin-
ium
Costs
The building cost for the school was approxi- mately US$8 per sq. ft. The total building cost was about HK$4,848,000. with a further HK$500.- 000 being spent on initial equipment and movable furnishings.
North elevation of classroom block with canopy protection at each floor
Below: Laboratory at sixth floor level and typical primary classroom unit
Large gymnasium occupying two floors beneath the covered playground area
Far East BUILDER, April 1968.
27