Excavate to

Set Out

Strip Sele

Red Levels

1

Fig. 4.

Fuild Manholes,

Excavate for

Drains

Lay Drains

60

Cone Fdns

70

Start xC. to Fdas

Finish Exe

to Fans

Start Bwk to DP.C.

40

50

tion

Hardcore to GF. Slat

Hlinding to G.F Slab

Finish Brickwork to DPC

Fwk to Gr. Beams

Reint to Gr Brams

Conc. to

Gr. Beams

120

30

Start Conr to G.F. Slab

150]

Roof

Structure

20

Roof Coverings

Exti

Plumbing

Erect Frame

10

Fig. 5.

Glazing

Carpentry

Elec

Wiring

30

Brick work

Partitions

vities are linked with others and form a closed circuit.

Dangling This occurs when an arrow is left suspended with no clos- ing activity.

Numbering Events

Ext! Plumbing

Errors such as Looping and Dang- ling can be avoided if a rigid number- ing routine is adopted. A method suggested by Fulkerson1 is both simple and logical.

Fulkerson's Routine

(1) Find the initial event and num- ber it. An initial event has

arrows emerging from it but none entering.

(2) Delete all arrows emerging from numbered events. This will create new initial events.

(3) Number all new initial events. (4) Delete all arrows emerging from the newly numbered events creat- ing more initial events. Carry on this process until all events have been numbered.

Using this routine, it will be found impossible to create new initial events in a network containing a Loop. Dangling will become obvious by the inspection required when carrying out the numbering.

A numbering system which in- creases in increments of five or ten leaves more scope for the insertion and subsequent numbering of ad- ditional activities, e.g. 11, 12, 13, etc.

Glazing

Extl Painting

Plastering

Extl Painting

Assigning Duration

о

Intl Painting

Having drawn the diagram and completed the numbering, the next step is to ascribe durations to the acti- vities. This should be done by con- sultation between planner and site engineer. For many operations, the work contents will be well known and reasonably accurate estimates can be given. In exceptional cases, work study study synthetics may be available. These can be used to build up dura- tion times.

Where the duration cannot be estimated with any certainty, the

PERT method of three time estimates can be used. The engineer should be asked to give three separate estimates of the possible duration.

i

Optimistic (O). The time the acti- vity would take assuming every-

Reinforcement to Cols

(3)

thing goes as well as it possibly

can.

ii Most Likely (M). The time the ac- tivity would take in normal cir-

cumstances.

iii Pessimistic (P). The time the acti- vity would take if nearly every- thing goes wrong.

The weighted average is then cal- culated from the formula:-

0 + 4M + P =

6

expected time (Te)

The PERT formula is based on the assumption that estimates of the duration follow a Beta distribution. There is a measure of disagreement among mathematicians on the com- plete validity of the assumptions made. in the establishment of the PERT formula for a detailed discussion of the PERT statistics, reference should be made to papers by Grubbs

Clark and Fulkerson.2

Having estimated the durations, these should be marked on the diag- ram for analysis.

Analysing The Diagram

The

runs

The system of analysis sorts jobs into critical and non-critical. chain of critical jobs which through the network is the critical path. There will always be at least one critical path. The duration of the project is controlled by cumulative durations of individual jobs on the critical path.

Earliest Event Times

Before an event is reached, all the activities leading to that event must be completed. This is achieved by

Fmwk to cols

Conc Cols

70

80

(3)

(2)

90

Bwk to roof level

Concrete Slab

and Stairs

50

60

(2)

Cure and Strike

(10)

(4)

Reinforcement to

Kitchen area

Concrete to Kitchen area

(110)

(120)

(4)

(6)

Fig. 6.

Fmwk to Kitchen area

(7)

(100)

48

Far East Architect & Builder June, 1967

Share This Page