13 Build Manholes

30

(6)

A

2 8 2.1.

Excavate for

Drains

(( 6 )

13

Lay Drains

60

(8)

EL. M/C

2. D. 2. L.

Hardcore to G.F Slat

10

Conc. Fons.

(5)

4 L

(6) /10\ 6. Conc.

23

0

3

5

}

16

Excavate to

Start exc.

Finish Exc

Set Out

Strip Site

Red Levels

to Fdns.

to Fdns

Start Bwk to D.P.C

Finish Brickwork to D.P C

[10

[(20

30

40

50

50

100

(2)

(2)

(3)

(4)

(7)

I.L.

I.L. M C

I.L. MIC

1.L. M/C

IL MC

4 B. 2.L.

(7)

4 B. 2...

Fwk, to Gr. Beams

26

Reint. to Gr. Beam<

28

120)

(130)

Fig. 8.

(3)

(2)

4 C. 2. L.

2. S. 2. L.

Table 3

28

3

34

Blinding to GF Slab

Start Cone to

G.F. Slab

110)-

140)

150

(1)

6. Conc

(4)

30

6 Conc.

Conc. to Gr Beams

(1)

& Conc

Example: Consider job

(40, 60) Excavate for drains.

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24

Duration Job (40, 60)

Total Float Job (40, 60)

Event

Alternative Path

Earlier

No.

Durations

Time

Earliest Start

time Job (40, 60)

| | | |

150

34

140

34-4

30

Max time available

Latest Finish time Job (40, 60)

130

30-1

29

120

29-2

27

Fig. 8(a)

110

30-1

29

100

29-5 or 30—7 or

Example: Consider job (40, 60) (Excavate for drains) in relation to job (60, 100) (Lay drains)

27-3

23

90

23-7

16

80

23-6

17

70

16-6

10

60

23- -8

15

Duration (40, 60)

50

10-0

10

1 2 3 4 5 6

7

8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24

Max time available.

Total Float (40, 60)

Max time available (60, 100)

Earliest Start time

40

10

-3 or 15-6 7

Job (40, 60)

30

7.

-2

5

20

5. -2

10

3-3

3

0

Earliest Start time

job (60, 100)

Duration Job (60. 100)

Interfering Floor (40, 60)

These latest times are entered on the network diagram and enclosed in triangles.

The activities with equal earliest and latest event times are the critical operations. The chain of critical operations which runs through the diagram constitute the critical path. This is usually distinguished by a double or thickened line.

The basic techniques so far consi- dered have assumed that the resources are unlimited and available as requir- ed. This will very seldom be the case in practice. Any plan which does not take into account the restrictions im- posed by the availability of resources will be of little practical value.

Resources can be made up of men at varying levels of responsibility em- ployed either on or off the site, plant in the form of excavators, cranes, con- crete-mixers, lorries, etc. and materials such as aggregates, cement, reinforce- ment, pipes, etc.

Any of these resources may not be available when required and will there- fore affect the project duration.

Float

In order to be able to reduce the

effect of fluctuating demand on re-

Fig. 8(b)

Example: Consider job (80, 100) Build manholes in relation to job (100, 140) Finish brickwork to D.P.C.

10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33

Earliest Start time Job (100,140)

Fig. 8(c)

Duration Job (80, 100)

Max time available

Earliest Start time Job (80, 100)

Duration Job (100,140)

Free Float Job (80 100)

Example: Consider job (50, 90) Finish excavation to founds in relation to job (90, 100) Start bwk to D.P.C.

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24

sources, it is important to know the Fig. 8(d)

Far East Architect & Builder July, 1967

Latest Finish

time Job (40, 50)

Duration Job (50, 90)

Earliest Start time Job (90, 100)

Max time available

Duration Job

Independent Floor Job (50, 90)

555

Share This Page