TH

HE basic network diagram is pre- pared on the assumption that resources are unlimited and available as required. As this will not be the situation in practice, it is necessary to smooth the possible fluctuating de- mand on the various types of re-

source.

Provided that the number of acti- vities is small and not too complicat- ed, manual methods of allocating resources can be used with reasonable results. One method of doing this is first to draw the arrow diagram to a time scale, as shown in Fig. 10, assuming that all activities start at their earliest times.

Vertical lines linking the activities preserve the sequence: dotted lines re-

floats. present dummies

and

As every activity is assumed to start at its earliest time, only free float is shown.

The time-scaled diagram shows clearly the number of jobs which are running parallel and, from this, the numbers of the resource under con- sideration can be plotted beneath the diagram in the form of a Histogram. This will show the fluctuation of de- mand on the resource. Fig. 10 shows

NETWORK ANALYSIS IN CONSTRUCTION

by P.A. Smith, AIOB

This is the last of the series of articles by Mr. P. A. Smith, who is a lecturer at Hong Kong Technical College. In it he des- cribes extensions of the basic technique of network analysis.

the fluctuation of demand on the re- source "Labourers”.

By moving activities within their float times, "peaks" in demand can be smoothed. Where an activity is on the critical path, any adjustment will extend the project time.

In the first instance, it is preferable to plot the Histogram for each re- source and attempt to do the "re- source levelling" without changing gang sizes or altering durations as these changes may create new critical paths.

An alternative method to Fig. 10 is shown in Fig. 11 this method is similar to that used in traditional bar charts. The total time available for carrying out the activity, i.e. the difference between Earliest start and Latest finish times are plotted as a continuous bar. The Earliest start plus the duration will give the Earliest Finish time and the portion remain- ing will be Total Float time.

Between

the Earliest start and

Latest finish times the actual sche- duled Start and Finish times as de- termined by resource requirements can be plotted.

If manual methods of resource levelling are carried out by an en- gineer with experience of bar-chart methods, this knowledge together with technical know-how can produce good results.

Although the method of levelling resources by making use of activity float times has been generally accept- ed, it has been shown by Kochanski3 that these methods can lead to un- economic solutions.

Use of Computers

A number of computer programmes are available for resource allocation. These programmes require that pri- ority rules specify the action to be taken when activities could be per- formed if the resources were avail- able.

Build Manholes

Float 4 Days

OR

2 8 2 L

Excavate for Drains

IL. MIC

Lay Drains

Float 2 Days

60

2 D. 2. L

I

70

Excavate to

Conc. Founds

6L

Start Bwk to D.P.C

90

(100)

4 B 2 L.

Set Out

Strip Site Red Levels

Start Exc. to Founds

Finish Exc. to Founds

to

20

30

40

50

1.L.

I.L. M/C I.L. M.C

I.L. M/C

I.L. M/C

Float 2 Days

LABOURERS

O-NWI

LABOURERS

CORN-O

All activities starting at their earliest limes

2

3

4

5 6

7

8

9

10

11

12 13

14

15

16

Resource levelled within float times

1

2

3

5

Fig. 10.

56

܂

17

་་

18

19 20 21

242

Start Conc to G F

Slab

40

[150]

6 L Conc to

Gr ¡Beam

Floats 1 Day

Finish Brickwork |lo_D.P.C.

8. 2. L. Reinft to

Form work to Ground Beam

Gr. Beam

120

4. C 2. L.

I

I Hardcore to G.F

4 L.

130 2.S.2.L. 6

Blinding to G.F

10

6 L.

23 24 25 26

27

28

29

30

31

32 33 34

10

11

12

13

14

15 16

17 18 19 20 21 22

23 24

25

26

27 28

29

30

31

12

33 34

days

Far East Architect & Builder August, 1967

Share This Page