Lengkuas siphon with the Central Canal crossing Sungei Podang Tarap

Pelubang (North) regulator

40

World Bank (International Bank for Reconstruction and Development) agreed to arrange a loan. Immediately the engineers were instructed to pro- ceed with the project and construction commenced in 1966. The work was virtually completed during 1969, with the exception of the installation of an electronic control system which will be completed this year.

As a result of these works, double cropping of rice began during the dry season of 1970 and this year irrigation of a greatly extended area will be pos sible. Torrential rains at the beginning of December and January have filled all the reservoirs.

Computer help

The investigations which eventually led to the irrigation project in its pre- sent form involved hydrological cal- culations based on rainfall records and river gauging over 18 years. These cal- culations simulated with the help of

Far East BUILDER, April 1971

Share This Page