214
No.
DRAINAGE — Contd.
Appendix IV - Contd.
Project
A
B
C
Stormwater Drains and Sewer, Chung Hom Kok Road DH17 Extension of Twin Box Culvert, Chai Wan Reclamation-Final Section DH18 Drainage and Road Works South of Central Areas, Chai Wan *DH19 Drainage Works at Middle and South Bay Beaches *DH20 Diversion of Stream Course under Pok Fu Lam Dump
DH14 Decking of Wong Nai Chung Nullah from Jockey Club to Leighton
Hill Road
DH15 Decking of Wun Sha Street Nullah above Tung Lo Wan Road *DH16
63/3
63/1
63/3
63/1
62/3
62/3
64/1
63/1
63/1
63/2
63/1
62/3
63/2
62/3
DH21
Construction of Main Stormwater Culvert in Western Chai Wan
Reclamation
63/1
DH24 Chung Hom Kok Sewerage Scheme
64/2
64/1
DH 9 included in RH67
* Completed Items
PORT WORKS AND DEVELOPMENT
PHI
PH2
Incineration Plant, Hong Kong Island (Consulting Engineers) Aberdeen Reclamation Model
62/NOV
60/3
59/3
63/3
PH3
Aberdeen Reclamation and Typhoon Shelter, Stage I
61/AUG 59/2
59/1
PH4
PH5
Aberdeen Reclamation and Typhoon Shelter, Stage II Central Reclamation, Stages II & IV
62/FEB
59/3
58/3
PH6
Chai Wan Seawall, Stage I
64/1
63/2
PH7
Kennedy Town Reclamation
64/3
64/2
61/2
PH8
Sandy Bay Reclamation, Stage I
63/3
PH9
Sandy Bay Reclamation, Stage II
64/1
63/3
PH10
Marine Police Pier and Access Road, Aberdeen
63/3
PH11
Reclamation and Breakwaters at Aldrich Bay
60/1
PH12
Public Pier and Concourse at Aldrich Bay
63/3
60/1
*PH13
Passenger Ferry Pier, North Point
60/3
60/1
PH14
Vehicular Ferry Piers (North Point to Kowloon City) (Consulting 57/1
Engineers)
PH15
Pok Fu Lam Development Investigation
62/3
PH17
Chai Wan Seawall, Stage II
63/2
PH18
Chai Wan Breakwaters
63/2
PH19
Wan Chai Reclamation, Stage II
64/1
PH20
PH21
Second Incinerator for Hong Kong Island Wan Chai Reclamation, Stage I
64/3
64/3
64/1
No.
* Completed Items
CIVIL ENGINEERING
KOWLOON AND NEW KOWLOON
Project
A
B
C
ROADS AND BRIDGES
*RK1
Airport Perimeter Road
57/2
RK2
Boundary Street/Tai Po Road/Cheung Sha Wan Road Junction
61/3
61/1
Improvements
RK3
Castle Peak Road—Provision of Additional Carriageway around Lai Chi
Kok Hospital
62/3
61/3
RK4
Construction of Cherry Street (Tong Mi Road to Tai Kok Tsui Road)
63/1
RK5
RK6
Cheung Sha Wan Road Extension (Ton Kin Street to Kom Tsuen Street) Choi Hung Road Improvements
59/3
64/3
63/2
RK7
Clearwater Bay Road (New Alignment from Lung Cheung Road to
Anderson Road)
63/2
RK8
Road Link between Cornwall Street and Yau Yat Chuen
63/1
62/3
RK9
Diamond Hill Loop Road
61/3
RK10
Reconstruction of Jordan Road (Nathan Road to Canton Road)
64/3
63/3
RK11
Extension of Aircraft Parking Apron, Kai Tak
64/1
63/3
RK12
Kwun Tong Road, Stage I
58/3
RK13 Kwun Tong Road, Stage IV
62/1
61/3
60/1
RK14
Kwun Tong New Town, Roads and Drainage for Housing Zones I, II &
III and Commercial Centre
59/2
RK15
Kwun Tong New Town, Roads and Drainage for Industrial Zone 5,
Section A
56/3
Page 220Page 221