50
Head 14—KOWLOON CANTON RAILWAY
Approved Estimate 1951-52
Sub-heads
Special Expenditure
Estimate 1952-53
30 Additions to Lo Wu Station
58,000
31 Duplicating equipment
32 Foundry building
1,000
33 Quarters at Yaumati
34 Relaying and renewal of permanent way
933,000
35 Sleeper incising shed
36 Wo Hop Shek cemetery scheme
71,000
Additions to quarters
Blackheads Point goods yard
Latrine
Overhead water supply
63,000
40,000
3,500
7,500
Rebuilding of coaches
150,000
Repairs to quarters ..
1,900
Repairs to Workshops
82,000
Strengthening of embankment
1,100
Total Special Expenditure
1,412,000
Total Expenditure
5,751,958
60
CA
1,200 (29)
700 1,000 (29) 77,000 (30) 720,000|(31)
5,000 1,000 (29)
(32)
(33)
805,900
5,193,370
(1) 1 supernumerary post for 4 days
(2) Provides for 1 post only
(3) 1 post provided for under Temporary staff (4) 2 posts not required
(5) Previously provided for under non-pensionable
establishment
(6) Title changed from Assistant Engineer (7) 3 posts not required
(8) 4 Office Attendants in place of 4 Store
Attendants
(9) 1 Office Attendant in place of 1 Messenger (10) Title changed from Female Attendant (11) Provides for:
5 Clerks
1 Railway Clerk (180)
(12) Personnel changed
(13) More acting appointments
(14) Previously provided for under Miscellaneous
allowances
(15) Previously overestimated
(16) Increased costs
(17) Title changed from Casual labour
(18) Previously provided for in part under Miscel
laneous allowances
(19) Economy measure
(20) Considered sufficient
(21) Provided for in part under Personal emolu.
ments and in part under Daily-rated staff
(22) Decreased traffic
(23) More publications
(24) Provided for in part under Miscellaneous
Services
(25) More confiscated stores
26) Previously omitted in error
(27) Fund not established
(28) Provided for under Police Force
(29) Retention money
(30) New project in place of Additions to quarter
(31) Continuation of programme
(32) Project cancelled
(33) Programme curtailed
Page 50Page 51