96
HONGKONG ESTIMATES
PUBLIC WORKS.
Original Revised Estimate.
Estimate.
Estimated Expenditure during 1919.
Estimated
Total Expen- Estimated,
diture to
31st Dec.,
1919.
Expenditure,
1920.
1.-PUBLIC WORKS,—Continued.
C.-PUBLIC WORKS, EXTRA- ORDINARY,-Contd.
Brought forward,..
BUILDINGS,-- Continued.
49 Additional Quarters in King's Park
area,
50 Tsimshatsui Police Station Exten-
51
sions,
Latrine adjoining Market Street,
Yaumati,.
COMMUNICATIONS.
52 Roads:
(a.) Main Roads in Kowloon,
(b.) Extending Coronation Road northwards through hill (for- merly K.F.L. 11),
(c.) Road to China Light and Power Co.'s new station,
(d.) General Works,................
DRAINAGE.
53 Training Nullahs:-
54
(a.) Argyle Street Nullah,-Con-
structing South wall & invert, . (b.) General Works,......
Miscellaneous Drainage Works,
LIGHTING.
55 Extensions of Lighting.....
MISCELLANEous.
56 Filling in Tidal Flat and cutting down hill between Taikoktsui and Fuk Tsun Heung,
57 Filling in low-lying area East of
Shanghai Street,....
58 Enlarging Playground at Kowloon
British School,
59 King's Park Quarters,-Installing
water-closets,
60 Chinese Cemeteries,-Laying out new
areas,
61
Miscellaneous Works,
PUBLIC HEALTH AND BUILDINGS
Ordinance, 1903.
62 Compensation and Resumptions,
WATER WORKS.
63 Substituting 18" main for existing 12" from Kowloon Filter Beds to Yaumati,
64 Enlarging mains to improve the dis-
tribution system in Kowloon,
65 Miscellaneous Water Works,
$
*
******
A
2,625,700
***
******
100,000
38,000
7,000
150,000
30,000
50,000
10,000
40,000
....
50,000
......
303,000
4,000
2,000
4.
10,000
...
10,000
30,000
•
1,500
30,000
30,000
4,000
2,000
*
1,000
7,000
O
50,000
175,000
..
......
Carried forward,..
..
150,000
50,000 8,000
3,424,200