Bay.
The other works are :—
1. Laying platform for third howitzer, two being already laid.
2. Epaulment for howitzer battery.
3. Field magazine for howitzer battery.
4. Entrenchments for infantry and field guns in Lyemun Bay and Sywan
5. Entrenchment on spur of Mount Parker.
6. Improvement of road communications.
The time and labour for these works, which would be executed by the troops, is estimated as follows :—
1st day
Entrenchments, Lyemun Bay Laying platform for howitzer
2nd 3rd
ور
4th 5th
29
Entrenchments, Sywan Bay, and on spur of Mount Parker; field magazine for howitzer battery
- Improving communications
Corps.
Officers.
N.C.O.'s and Men.
Royal Engineers Infantry
5
•
2
200
Same parties.
Ditto.
Twenty coolies would be employed during the third and fourth days carrying materials for the magazine.
tents.
Mat-sheds will be built by contract in about twenty days to replace the
Engineer District. This section is, with Sections VIII and X, in the C Engineer district, under the general Engineer supervision of Captain Stewart, Royal Engineers.
Tools. The tools required are enumerated in Schedule XVIII (9), and will be issued with the camp equipment.