290
-
(6) In addition to the list of works, notes have been added on individual works and a schedule is attached showing as accurately as possible the sums it is estimated will be spent on the various works in each year from 1938 to 1943.
(1) Government House
(2) City Development
LIST OF WORKS.
(3) Infectious Diseases Hospital
(4) Kowloon Hospital (Extension)
Estimated Cost.
$
2.000.000
1.000.000*
1,000,000
2,000,000
(5) Addition to Vehicular Ferry Piers (including reclamation
and resumption)
(6) Improvements to Canton through Road from Castle Peak
Road to Mah Fu Ferry including new Quarry
585,000
2,200,000
(7) Government Quarters
1,000,000
(8) Air Raid Precautions
1,000,000
(9
(५){
New Peak School
160,000
Peak Bungalows
150,000
(10) Rebuilding of Police Stations and Police Training School
700,000
(11) New Garages and Quarters at Kennedy Town
100,000
(12) Protective Works, Causeway Bay Typhoon Shelter
140,000
12,035,000
Compensations and resumptions connected with the
above
1,100,000
Total
13,135,000
*To be spent in the period 1938-43.
NOTES.
(1) Government House.-A separate memorandum on this which has
already been circulated appears as an annexure hereto.
(2) City Development. It is probable that by 1943 considerable pro- gress in the development of the site now occupied by the Secretariat, P.W.D. and Volunteer Headquarters and of the St. John's Place area will have been made. The figure of $1,000,000 should be regarded
as a token sum.
(3) Infectious Diseases Hospital.-Recent experience suggests the neces- sity of providing more accommodation than previously contemplated and the estimate has been increased accordingly.
(4) Kowloon Hospital Extension.-Revised plans are now under considera- tion and the estimate is very approximate. Assuming the continued development of Kowloon the provision of increased hospital accom- modation is a necessity. The ultimate completion of buildings and equipment may require still further provision.
Page 300Page 301