73
The following table gives in compact form my proposals, with a programme of work and costs:
PROGRAMME OF WORK & ESTIMATES.
Com- Com-
Estimated Estimated
mence.
plete.
Work.
Year.
Year.
Estimated Production. Cost.
Time to construct. Mill, Galls.
Remarks.
3
per day.
Aberdeen Scheme.
Upper Dam.
East Catchwaters
West
900,000
135,000
255,000
Supply Pipe to
Pumping Station... Pumping Station to
complete
270,000
190,000
Rising Mains
70,000
New Filters..
180,000
Existing Dam Alter-
ation
1928 1931
3 years.
2.12
100,000
Line....
30,000
497,000
Lower Dan Pipe
Bennet's Hill Catch-
water
Alteration to Pok-
fulam Reservoir
Access Road
Resumptions
Salvage
Mt. Parker Catch-
water
Mt. Pottinger Catch-
water
Tytam Tuk (East)
Catchwater...
Dragon's Back (East)
Catchwater
Shing Mun Scheme !
(1st Section).
170,000
1929
1932
3 years.
1.5
160,000
180,000
180,000
Rapid Gravity Filters
1927
1928 11⁄2 years.
Land Pipe Line
1927 1929 2
2
Service Reservoir
i
(Sheklaipui)
1928
1930
Cross Harbour Pipe...
1928
1929
11
A
H.K. Garden Service
Reservoir
1929
1931
1호
Carried forward.
84,000
Under Construction.
""
375,000
2.5†<
Money required to
complete including 1928
expenditure.
400,000
300,000*
400,000
3.62
$4,876,000
*Scheme proposed is for one 12′′ dia, steel main capable of passing 32 million gallons per day laid on Harbour
bottom without dredging to cost $250.000.
The Consulting Engineers Scheme is for two 18" dia. steel mains with a combined capacity of fully 8 million gallons per day laid in a dredged trench and covered with concrete to cost £200,000, or £165,000 if Government assumes responsibility for all risks. +Already included in "Estimate of Capacity" of 5 million gallons per day for the existing supply for Kowloon.