NEW SAIYINGPUN SCHOOL.

CONTRACT No. 49 or 1923. CONTRACTORS: MESSRS. KIN LEE & Co.

3rd Quarterly Report ending 31st March, 1925.

Laid before the Legislative Council by Command of His Excellency the Governor on the 14th May, 1925.

Satisfactory progress has been made during the past three months and the top storey level has now been reached.

On the South Class Room Block the brickwork is carried up about 6′ 0′′ above floor level. The whole of the R.C.C. floors are laid except to Science Block, where the casing only is fixed. Special attention has been taken in regard to floor channels to take Gas and Water pipes and waste in Science Laboratories in order to obviate cutting or drilling floors after being laid.

The Fire Department was consulted in regard to the Scheme generally, from a Fire Safety point of view, and on its recommendation it has been decided to put in an addi- tional Exit (and entrance) to Hing Hon Road. This is a very wise precaution particu- larly as a large proportion of the boys come from this Quarter.

The work done to date is of the highest standard and it was anticipated that the roof would be on by the end of May. The recent rains have, however, unfortunately stopped all outside work, and delayed the work about a month. A certain amount of internal plastering has been completed.

14th April, 1925,

HAROLD T. CREASY,

Director of Public Works.