HONGKONG,
TYPHOON REFUGE.
STATEMENT TO 31ST DECEMBER, 1911,
(vide pages 10 and 11 of Hansard, 23rd February, 1911).
4
No. 1912
Laid before the Legislative Council by Command of His Excellency the Governor, March 7th, 1912.
Contract time for completion-5 years from the 27th October, 1910.
Contract price,-
.$2,018,002
Cost of Contractor's extras other than those for
which provision is made in the Contract,...... Nil.
Total amount of Contract and Extras, ...$2.018,002
Divided into 60 months,.
14 months at $33,633,
Amount earned by Contractor on work actually accomplished including sum retained under the provisions of the Contract in the hands of the Government.............
33,633 per month.
$ 470,862
.$ 337,198
13th January, 1912.
W. CHATHAM, Director of Public Works.