APPENDIX DD

NEW TERRITORIES DEVELOPMENT DEPARTMENT

PROJECTS ON WHICH CONSTRUCTION CONTINUED OR COMMENCED

DURING 1976/77

Project Approximate Cost $ Sha Tin new town - Stage I, phase 1 87,800,000 Sha Tin new town Stage I, phase 2 development of areas 5, 28 and 48 180,800,000 Sha Tin new town Stage I, phase 2 development of areas 8C, 21 and 26B 68,700,000 Sha Tin new town Stage I, phase 2 formation of area 47B and adjacent trunk roads and sewers 114,000,000 Sha Tin new town Stage I, phase 2 development of area 16B 77,500,000 Sha Tin new town - Stage I, phase 2 development of area 14 and trunk road T1(part) - Tsuen Wan North development Stage I 188,860,000 Tsuen Wan North development - Stage II 67,000,000 Tsing Yi development Stage I 25,000,000 Kwai Chung Development, site formation roads and drainage for Ha Kwai Chung Estate 105,000,000 Castle Peak Housing Authority estate, area 6 23,000,000 Government office at Tuen Mun 132,900,000 Beach building Cafeteria Beach 2,700,000 Tuen Mun divisional police station 657,100 Tuen Mun new town - stage IA 12,100,000 Tuen Mun new town engineering development, stage IB, package 2 47,800,000 Tuen Mun new town engineering development, stage IB, package 5 5,350,000 5,540,000

246

Edit History

2026-05-12 09:58:12 · NVIDIA / meta/llama-4-maverick-17b-128e-instruct
Live
View comparison
AI Proofread
APPENDIX DD NEW TERRITORIES DEVELOPMENT DEPARTMENT PROJECTS ON WHICH CONSTRUCTION CONTINUED OR COMMENCED DURING 1976/77 Project Approximate Cost $ Sha Tin new town - Stage I, phase 1 87,800,000 Sha Tin new town Stage I, phase 2 development of areas 5, 28 and 48 180,800,000 Sha Tin new town Stage I, phase 2 development of areas 8C, 21 and 26B 68,700,000 Sha Tin new town Stage I, phase 2 formation of area 47B and adjacent trunk roads and sewers 114,000,000 Sha Tin new town Stage I, phase 2 development of area 16B 77,500,000 Sha Tin new town - Stage I, phase 2 development of area 14 and trunk road T1(part) - Tsuen Wan North development Stage I 188,860,000 Tsuen Wan North development - Stage II 67,000,000 Tsing Yi development Stage I 25,000,000 Kwai Chung Development, site formation roads and drainage for Ha Kwai Chung Estate 105,000,000 Castle Peak Housing Authority estate, area 6 23,000,000 Government office at Tuen Mun 132,900,000 Beach building Cafeteria Beach 2,700,000 Tuen Mun divisional police station 657,100 Tuen Mun new town - stage IA 12,100,000 Tuen Mun new town engineering development, stage IB, package 2 47,800,000 Tuen Mun new town engineering development, stage IB, package 5 5,350,000 5,540,000 246
Baseline (Original)
APPENDIX DD NEW TERRITORIES DEVELOPMENT DEPARTMENT PROJECTS ON WHICH CONSTRUCTION CONTINUED OR COMMENCED DURING 1976/77 Project Sha Tin new town - Stage I, phase 1 Sha Tin new town Stage I, phase 2 development of areas 5, 28 and 48 - Sha Tin new town Stage I, phase 2 development of areas 8C, 21 and 26B - - Sha Tin new town Stage I, phase 2 formation of area 47B and adjacent trunk roads and sewers Approximate Cost $ 87,800,000 180,800,000 68,700,000 114,000,000 - Sha Tin new town Stage I, phase 2 - development of area 16B 77,500,000 Sha Tin new town - Stage I, phase 2 development of area 14 and trunk road T1(part) Tsuen Wan North development Stage I - - 188,860,000 67,000,000 Tsuen Wan North development - Stage II 25,000,000 Tsing Yi development Stage I 105,000,000 Kwai Chung Development, site formation roads and drainage for Ha Kwai Chung Estate 23,000,000 Castle Peak Housing Authority estate, area 6 132,900,000 Government office at Tuen Mun 2,700,000 Beach building Cafeteria Beach 657,100 Tuen Mun divisional police station 12,100,000 Tuen Mun new town - stage IA 47,800,000 Tuen Mun new town engineering development, stage IB, package 2 5,350,000 Tuen Mun new town engineering development, stage IB, package 5 5,540,000 246
2026-05-12 09:58:12 · Baseline
View content

APPENDIX DD

NEW TERRITORIES DEVELOPMENT DEPARTMENT

PROJECTS ON WHICH CONSTRUCTION CONTINUED OR COMMENCED

DURING 1976/77

Project

Sha Tin new town

-

Stage I, phase 1

Sha Tin new town Stage I, phase 2 development of areas 5, 28 and 48

-

Sha Tin new town Stage I, phase 2

development of areas 8C, 21 and 26B

-

-

Sha Tin new town Stage I, phase 2 formation

of area 47B and adjacent trunk roads and sewers

Approximate

Cost

$

87,800,000

180,800,000

68,700,000

114,000,000

-

Sha Tin new town Stage I, phase 2

-

development

of area 16B

77,500,000

Sha Tin new town - Stage I, phase 2 development

of area 14 and trunk road T1(part)

Tsuen Wan North development Stage I

-

-

188,860,000

67,000,000

Tsuen Wan North development

-

Stage II

25,000,000

Tsing Yi development Stage I

105,000,000

Kwai Chung Development, site formation roads

and drainage for Ha Kwai Chung Estate

23,000,000

Castle Peak Housing Authority estate, area 6

132,900,000

Government office at Tuen Mun

2,700,000

Beach building Cafeteria Beach

657,100

Tuen Mun divisional police station

12,100,000

Tuen Mun new town

-

stage IA

47,800,000

Tuen Mun new town engineering development,

stage IB, package 2

5,350,000

Tuen Mun new town engineering development,

stage IB, package 5

5,540,000