APPENDIX DD
NEW TERRITORIES DEVELOPMENT DEPARTMENT
PROJECTS ON WHICH CONSTRUCTION CONTINUED OR COMMENCED
DURING 1975/76
Project ApproximateAPPENDIX DD
NEW TERRITORIES DEVELOPMENT DEPARTMENT
PROJECTS ON WHICH CONSTRUCTION CONTINUED OR COMMENCED
DURING 1975/76
Approximate
Project
Cost
$
Sha Tin New Town
Sha Tin New Town
Stage I, phase 2
development of areas 5, 48 and 28.
Sha Tin New Town - Stage I, phase 2
development of areas 80, 21 and 26B
Sha Tin New Town - Stage I, phase 2
-
Stage I, phase 1
87,800,000
180,800,000
68,700,000
formation of area 47B and adjacent trunk roads and sewers
114,000,000
Ha Kwai Chung Housing Authority estate, site formation,
roads and drainage
18,700,000
Tsuen Wan North development
Stage I
67,300,000
Tsing Yi development
-
Stage I
43,400,000
Castle Peak Housing Authority estate, area 6
132,900,000
Tuen Mun New Town Stage IA
49,000,000
Castle Peak Road through Castle Peak -
San Hui to Fu Tei
6,040,000
Tuen Mun New Town engineering development,,
Stage IB, package 2
5,350,000
Tuen Mun New Town engineering development,
Stage IB, package 5
5,540,000
Tuen Mun New Town engineering development,
Stage IB, package 8
137,500,000
Controlled tipping of refuse at Siu Lang Shui
9,750,000
-
Tuen Mun Road
Stage I
Tuen Mun water supply, Stage IP
304,000,000
47,900,000