# APPENDIX R

CIVIL ENGINEERING OFFICE

PROJECTS UNDERTAKEN BY CONSULTING ENGINEERS

Project Consulting Engineers Kai Tak Airport, Extension of Runway Messrs. Scott Wilson Kirkpatrick and Partners Runway Grooving Trials at Hong Kong Airport do. Extension of Aircraft Parking Apron and Taxiways, Hong Kong Airport Stage III - do Airport Tunnel Road, Mok Cheong Street to Kowloon Bay Reclamation do Aerodrome Lighting Control and Improvements to the Approach Lighting System of Runway 13, Hong Kong Airport Investigation - do - 10 Kwai Chung Reclamation (Culvert) - Improvements at North West Approach Lighting, Runway 13, Hong Kong Airport · do Clear Water Bay Road Development - do Sewage Treatment and Disposal, North West Kowloon - Investigation - Shek Wu Hui Pilot Sewage Treatment Plant Messrs. W. Szeto & Partners Sha Tin New Town - Interim Sewage Treatment Works - Investigation & Design Messrs. Watson (Hong Kong) Sha Tin New Town - Permanent Sewage Treatment Works Stage I - Design · do New Territories Stream Pollution Study do Landslide Study Phase II Messrs. Binnie & Partners (H.K.) do 194

Edit History

2026-05-12 08:02:09 · NVIDIA / meta/llama-4-maverick-17b-128e-instruct
Live
View comparison
AI Proofread
# APPENDIX R CIVIL ENGINEERING OFFICE PROJECTS UNDERTAKEN BY CONSULTING ENGINEERS Project Consulting Engineers Kai Tak Airport, Extension of Runway Messrs. Scott Wilson Kirkpatrick and Partners Runway Grooving Trials at Hong Kong Airport do. Extension of Aircraft Parking Apron and Taxiways, Hong Kong Airport Stage III - do Airport Tunnel Road, Mok Cheong Street to Kowloon Bay Reclamation do Aerodrome Lighting Control and Improvements to the Approach Lighting System of Runway 13, Hong Kong Airport Investigation - do - 10 Kwai Chung Reclamation (Culvert) - Improvements at North West Approach Lighting, Runway 13, Hong Kong Airport · do Clear Water Bay Road Development - do Sewage Treatment and Disposal, North West Kowloon - Investigation - Shek Wu Hui Pilot Sewage Treatment Plant Messrs. W. Szeto & Partners Sha Tin New Town - Interim Sewage Treatment Works - Investigation & Design Messrs. Watson (Hong Kong) Sha Tin New Town - Permanent Sewage Treatment Works Stage I - Design · do New Territories Stream Pollution Study do Landslide Study Phase II Messrs. Binnie & Partners (H.K.) do 194
Baseline (Original)
APPENDIX R CIVIL ENGINEERING OFFICE PROJECTS UNDERTAKEN BY CONSULTING ENGINEERS Project Kai Tak Airport, Extension of Runway Runway Grooving Trials at Hong Kong Airport Extension of Aircraft Parking Apron and Taxiways, Hong Kong Airport Stage III Airport Tunnel Road, Mok Cheong Street to Kowloon Bay Reclamation Aerodrome Lighting Control and Improvements to the Approach Lighting System of Runway 13, Hong Kong Airport Investigation 10 Kwai Chung Reclamation (Culvert) Improvements at North West Approach Lighting, Runway 13, Hong Kong Airport Clear Water Bay Road Development Sewage Treatment and Disposal, North West Kowloon - Investigation Shek Wu Hui Pilot Sewage Treatment Plant Sha Tin New Town - Interim Sewage Treatment Works - Investigation & Design Sha Tin New Town - Permanent Sewage Treatment Works Stage I - Design New Territories Stream Pollution Study Landslide Study Phase II Consulting Engineers Messrs. Scott Wilson Kirkpatrick and Partners do. - do do - do - - · do - do Messrs. W. Szeto & Partners Messrs. Watson (Hong Kong) · do do - do - Messrs. Binnie & Partners (H.K.) do 194
2026-05-12 08:02:09 · Baseline
View content

APPENDIX R

CIVIL ENGINEERING OFFICE

PROJECTS UNDERTAKEN BY CONSULTING ENGINEERS

Project

Kai Tak Airport, Extension of Runway

Runway Grooving Trials at Hong Kong

Airport

Extension of Aircraft Parking Apron and Taxiways, Hong Kong Airport Stage III

Airport Tunnel Road, Mok Cheong Street

to Kowloon Bay Reclamation

Aerodrome Lighting Control and

Improvements to the Approach Lighting System of Runway 13, Hong Kong Airport Investigation

10

Kwai Chung Reclamation (Culvert)

Improvements at North West Approach

Lighting, Runway 13, Hong Kong Airport

Clear Water Bay Road Development

Sewage Treatment and Disposal, North

West Kowloon - Investigation

Shek Wu Hui Pilot Sewage Treatment

Plant

Sha Tin New Town - Interim Sewage

Treatment Works - Investigation & Design

Sha Tin New Town - Permanent Sewage

Treatment Works Stage I - Design

New Territories Stream Pollution Study

Landslide Study Phase II

Consulting Engineers

Messrs. Scott Wilson Kirkpatrick

and Partners

do.

- do

do

- do -

-

· do

- do

Messrs. W. Szeto & Partners

Messrs. Watson (Hong Kong)

· do

do

- do

-

Messrs. Binnie & Partners (H.K.)

do

194