1975-1976 — Page 157

Public Works Department Annual Report 工務司署年報 All AI Reviewed

# NEW TERRITORIES DEVELOPMENT DEPARTMENT GENERAL OPERATION AND ORGANISATION CHART

145

## GENERAL

THE PLANNING AND IMPLEMENTATION OF THE PUBLIC WORKS PROGRAMME IN RESPECT OF SITE DEVELOPMENT INFRASTRUCTURE AND HOUSING UNDERTAKEN BY PWO IN THE NEW TOWNS AND FOR OTHER BUILDING AND ENGINEERING DEVELOPMENT SCHEMES IN THE NEW TERRITORIES

## SHATIN NEW TOWN DEVELOPMENT OFFICE

## TSUEN WAN NEW TOWN DEVELOPMENT OFFICE

## TUEN MUN NEW TOWN DEVELOPMENT OFFICE

## NEW TERRITORIES DEVELOPMENT BRANCH

1 PREPARATION OF OVERALL BALANCED DEVELOPMENT PROGRAMMES FOR THE NEW TOWNS

2 PREPARATION OF DETAILED LAYOUTS DEVELOPMENT PLANS AND DEVELOPMENT PROGRAMMES FOR ENGINEERING WORKS AND BUILDINGS TO BE CONSTRUCTED BY CONSULTANTS OR BY THE AO

3 LIAISON WITH NTA AND HD IN ORDER THAT LAND ACQUISITION AND CLEARANCE PROGRAMMES ARE IMPLEMENTED IN THE SEQUENCE REQUIRED FOR ENGINEERING AND BUILDING PROGRAMMES TO PROCEED ON SCHEDULE

4 CO-ORDINATION OF WORK OF UTILITY UNDERTAKERS AND THE ACTIVITIES OF PRIVATE DEVELOPERS WHERE THESE AFFECT THE OVERALL PROGRAMME OF WORKS

1 PREPARATION OF OVERALL BALANCED DEVELOPMENT PROGRAMMES FOR THE TERRITORIES RURAL CENTRES

2 PREPARATION OF DETAILED LAYOUTS DEVELOPMENT PLANS AND DEVELOPMENT PROGRAMMES FOR ENGINEERING WORKS AND BUILDINGS TO BE CONSTRUCTED BY CONSULTANTS OR BY THE AO

3 LIAISON WITH NTA AND HD IN ORDER THAT LAND ACQUISITION AND CLEARANCE PROGRAMMES ARE IMPLEMENTED IN THE SEQUENCE REQUIRED FOR ENGINEERING AND BUILDING PROGRAMMES TO PROCEED ON SCHEDULE

4 CO-ORDINATION OF WORK OF UTILITY UNDERTAKERS AND THE ACTIVITIES OF PRIVATE DEVELOPERS WHERE THESE AFFECT THE OVERALL PROGRAMME OF WORKS & INVESTIGATING AND MAKING RECOMMENDATIONS ON DEVELOPMENT PROPOSALS IN THE NEW TERRITORIES

Edit History

2026-05-12 07:41:22 · NVIDIA / meta/llama-4-maverick-17b-128e-instruct
Live
View comparison
AI Proofread
# NEW TERRITORIES DEVELOPMENT DEPARTMENT GENERAL OPERATION AND ORGANISATION CHART 145 ## GENERAL THE PLANNING AND IMPLEMENTATION OF THE PUBLIC WORKS PROGRAMME IN RESPECT OF SITE DEVELOPMENT INFRASTRUCTURE AND HOUSING UNDERTAKEN BY PWO IN THE NEW TOWNS AND FOR OTHER BUILDING AND ENGINEERING DEVELOPMENT SCHEMES IN THE NEW TERRITORIES ## SHATIN NEW TOWN DEVELOPMENT OFFICE ## TSUEN WAN NEW TOWN DEVELOPMENT OFFICE ## TUEN MUN NEW TOWN DEVELOPMENT OFFICE ## NEW TERRITORIES DEVELOPMENT BRANCH 1 PREPARATION OF OVERALL BALANCED DEVELOPMENT PROGRAMMES FOR THE NEW TOWNS 2 PREPARATION OF DETAILED LAYOUTS DEVELOPMENT PLANS AND DEVELOPMENT PROGRAMMES FOR ENGINEERING WORKS AND BUILDINGS TO BE CONSTRUCTED BY CONSULTANTS OR BY THE AO 3 LIAISON WITH NTA AND HD IN ORDER THAT LAND ACQUISITION AND CLEARANCE PROGRAMMES ARE IMPLEMENTED IN THE SEQUENCE REQUIRED FOR ENGINEERING AND BUILDING PROGRAMMES TO PROCEED ON SCHEDULE 4 CO-ORDINATION OF WORK OF UTILITY UNDERTAKERS AND THE ACTIVITIES OF PRIVATE DEVELOPERS WHERE THESE AFFECT THE OVERALL PROGRAMME OF WORKS 1 PREPARATION OF OVERALL BALANCED DEVELOPMENT PROGRAMMES FOR THE TERRITORIES RURAL CENTRES 2 PREPARATION OF DETAILED LAYOUTS DEVELOPMENT PLANS AND DEVELOPMENT PROGRAMMES FOR ENGINEERING WORKS AND BUILDINGS TO BE CONSTRUCTED BY CONSULTANTS OR BY THE AO 3 LIAISON WITH NTA AND HD IN ORDER THAT LAND ACQUISITION AND CLEARANCE PROGRAMMES ARE IMPLEMENTED IN THE SEQUENCE REQUIRED FOR ENGINEERING AND BUILDING PROGRAMMES TO PROCEED ON SCHEDULE 4 CO-ORDINATION OF WORK OF UTILITY UNDERTAKERS AND THE ACTIVITIES OF PRIVATE DEVELOPERS WHERE THESE AFFECT THE OVERALL PROGRAMME OF WORKS & INVESTIGATING AND MAKING RECOMMENDATIONS ON DEVELOPMENT PROPOSALS IN THE NEW TERRITORIES
Baseline (Original)
NEW TERRITORIES DEVELOPMENT DEPARTMENT GENERAL OPERATION AND ORGANISATION CHART 145 GENERAL THE PLANNING AND IMPLEMENTATION OF THE PUBLIC WORKS PROGRAMME IN RESPECT OF SITE DEVELOPMENT INFRASTRUCTURE AND HOUSING UNDERTAKEN BY PWO IN THE NEW TOWNS AND FOR OTHER BUILDING AND ENGINEERING DEVELOPMENT SCHEMES IN THE NEW TERRITORIES SHATIN NEW TOWN DEVELOPMENT OFFICE TSUEN WAN NEW TOWN DEVELOPMENT OFFICE TUEN MUN NEW TOWN DEVELOPMENT OFFICE NEW TERRITORIES DEVELOPMENT BRANCH 1 PREPARATION OF OVERALL BALANCED DEVELOPMENT PROGRAMMES FOR THE NEW TOWNS BUILDINGS 2 PREPARATION OF DETAILED LAYOUTS DEVELOPMENT PLANS AND DEVELOPMENT PROGRAMMES FOR ENGINEERING WORKS AND TO BE CONSTRUCTED BY CONSULTANTS OR BY THE A O 9 LIAISON WITH NTA AND H D IN ORDER THAT LAND ACQUISITION AND CLEARANCE PROGRAMMES ARE IMPLEMENTED IN THE SEQUENCE REQUIRED FOR ENGINEERING AND BUILDING PROGRAMMES TO PROCEED ON SCHEDULE 4 CO-ORDINATION OF WORK OF UTILITY UNDERTAKERS AND THE ACTIVITIES OF PRIVATE DEVELOPERS WHERE THESE AFFECT THE OVERALL PROGRAMME OF WORKS 1 PREPARATION OF OVERALL BALANCED DEVELOPMENT PROGRAMMES FOR THE TERRITORIES RURAL CENTRES NEW 2 PREPARATION OF DETAILED LAYOUTS DEVELOPMENT PLANS AND DEVELOPMENT PROGRAMMES FOR ENGINEERING WORKS AND BUILDINGS TO BE CONSTRUCTED BY CONSULTANTS OR BY THE A O 3 LIAISON WITH NTA AND HD IN ORDER THAT LAND ACQUISITION AND CLEARANCE PROGRAMMES ARE IMPLEMENTED IN THE SEQUENCE REQUIRED FOR ENGINEERING AND BUILDING PROGRAMMES TO PROCEED ON SCHEDULE 4 CO-ORDINATION OF WORK OF UTILITY UNDERTAKERS AND THE ACTIVITIES OF PRIVATE DEVELOPERS WHERE THESE AFFECT THE OVERALL PROGRAMME OF WORKS $ INVESTIGATING AND MAKING RECOMMENDATIONS ON DEVELOPMENT PROPOSALS IN THE NEW TERRITORIES
2026-05-12 07:41:22 · Baseline
View content

NEW TERRITORIES DEVELOPMENT DEPARTMENT GENERAL OPERATION AND ORGANISATION CHART

145

GENERAL

THE PLANNING AND IMPLEMENTATION OF THE PUBLIC WORKS PROGRAMME IN RESPECT OF SITE DEVELOPMENT INFRASTRUCTURE AND HOUSING UNDERTAKEN BY PWO IN THE NEW TOWNS AND FOR OTHER BUILDING AND ENGINEERING DEVELOPMENT SCHEMES IN THE NEW TERRITORIES

SHATIN NEW TOWN DEVELOPMENT OFFICE

TSUEN WAN NEW TOWN DEVELOPMENT OFFICE

TUEN MUN NEW TOWN DEVELOPMENT OFFICE

NEW TERRITORIES

DEVELOPMENT BRANCH

1 PREPARATION OF OVERALL BALANCED DEVELOPMENT PROGRAMMES FOR THE NEW TOWNS

BUILDINGS

2 PREPARATION OF DETAILED LAYOUTS DEVELOPMENT PLANS AND DEVELOPMENT PROGRAMMES FOR ENGINEERING WORKS AND TO BE CONSTRUCTED BY CONSULTANTS OR BY THE A O

9 LIAISON WITH NTA AND H D IN ORDER THAT LAND ACQUISITION AND CLEARANCE PROGRAMMES ARE IMPLEMENTED IN THE SEQUENCE REQUIRED FOR ENGINEERING AND BUILDING PROGRAMMES TO PROCEED

ON SCHEDULE

4 CO-ORDINATION OF WORK OF UTILITY UNDERTAKERS AND THE ACTIVITIES OF PRIVATE DEVELOPERS WHERE THESE AFFECT THE OVERALL PROGRAMME OF WORKS

1 PREPARATION OF OVERALL BALANCED DEVELOPMENT PROGRAMMES FOR THE TERRITORIES RURAL CENTRES

NEW

2 PREPARATION OF DETAILED LAYOUTS DEVELOPMENT PLANS AND DEVELOPMENT PROGRAMMES FOR ENGINEERING WORKS AND BUILDINGS TO BE CONSTRUCTED BY CONSULTANTS OR BY THE A O

3 LIAISON WITH NTA AND HD IN ORDER THAT LAND ACQUISITION AND CLEARANCE PROGRAMMES ARE IMPLEMENTED IN THE SEQUENCE REQUIRED FOR ENGINEERING AND BUILDING PROGRAMMES TO PROCEED ON SCHEDULE

4 CO-ORDINATION OF WORK OF UTILITY UNDERTAKERS AND THE ACTIVITIES OF PRIVATE DEVELOPERS WHERE THESE AFFECT THE OVERALL PROGRAMME OF WORKS $ INVESTIGATING AND MAKING RECOMMENDATIONS ON DEVELOPMENT PROPOSALS IN THE NEW TERRITORIES