1973-1974 — Page 1634

Public Works Department Annual Report 工務司署年報 All AI Reviewed

11.106

The Unit is responsible for liaising with the Consulting Engineers engaged on water supply schemes other than desalting. Expenditure during the year amounted to over $203 million.

High Island Water Scheme

11.107

Satisfactory progress was maintained despite the world-wide crisis on fuel and oil products.

11.108 The Kwun Mun strait was closed by cofferdams, which form the permanent protective works to the main dams. Excavation for the foundation of the West Dam was in progress.

11.109

Progress in the construction of tunnels and intakes continued satisfactorily.

Raising of Plover Cove Dams, Uprating and Extension of Sha Tin Treatment Works and Pumping Station and Tai Po Tau Pumping Station

11.110

Raising of the dams and associated works at Plover Cove Reservoir were completed. Grouting to the Saddle Dam was found necessary in order to seal off seepage which was discovered when the Reservoir was filled to its top water level for the first time in September 1973.

11.111

Civil engineering works and installation of pumping plant associated with the extension of Sha Tin Treatment Works and Pumping Station were completed and the new pumpsets and clarifiers put into service. Installation of electrical and chemical plant was in hand.

11.112 At Tai Po Tau Pumping Station, installation of the pumping plants, band screens and ancillary mechanical plant was completed. Commissioning of the tunnel gates was delayed pending the delivery of the electrical switchgear from the United Kingdom.

River Training Works at Tai Po

11.113 The feasibility report submitted by the consulting engineers was accepted and an item included in the Public Works Programme for its implementation by the Civil Engineering Office.

North Western Water Scheme - Pollution Study

11.114 The Report submitted by the consulting engineers was considered by the Public Works Sub-Committee and it was decided that because of the polluted state of the streams, no action would be taken at the present time although the potential benefits of the scheme would be kept in mind.

Edit History

2026-05-12 05:53:01 · NVIDIA / meta/llama-4-maverick-17b-128e-instruct
Live
View comparison
AI Proofread
11.106 The Unit is responsible for liaising with the Consulting Engineers engaged on water supply schemes other than desalting. Expenditure during the year amounted to over $203 million. High Island Water Scheme 11.107 Satisfactory progress was maintained despite the world-wide crisis on fuel and oil products. 11.108 The Kwun Mun strait was closed by cofferdams, which form the permanent protective works to the main dams. Excavation for the foundation of the West Dam was in progress. 11.109 Progress in the construction of tunnels and intakes continued satisfactorily. Raising of Plover Cove Dams, Uprating and Extension of Sha Tin Treatment Works and Pumping Station and Tai Po Tau Pumping Station 11.110 Raising of the dams and associated works at Plover Cove Reservoir were completed. Grouting to the Saddle Dam was found necessary in order to seal off seepage which was discovered when the Reservoir was filled to its top water level for the first time in September 1973. 11.111 Civil engineering works and installation of pumping plant associated with the extension of Sha Tin Treatment Works and Pumping Station were completed and the new pumpsets and clarifiers put into service. Installation of electrical and chemical plant was in hand. 11.112 At Tai Po Tau Pumping Station, installation of the pumping plants, band screens and ancillary mechanical plant was completed. Commissioning of the tunnel gates was delayed pending the delivery of the electrical switchgear from the United Kingdom. River Training Works at Tai Po 11.113 The feasibility report submitted by the consulting engineers was accepted and an item included in the Public Works Programme for its implementation by the Civil Engineering Office. North Western Water Scheme - Pollution Study 11.114 The Report submitted by the consulting engineers was considered by the Public Works Sub-Committee and it was decided that because of the polluted state of the streams, no action would be taken at the present time although the potential benefits of the scheme would be kept in mind.
Baseline (Original)
11.106 The Unit is responsible for liaising with the Consulting Engineers engaged on water supply schemes other than desalting. Expenditure during the year amounted to over $203 million. High Island Water Scheme 11.107 Satisfactory progress was maintained despite the world-wide crisis on fuel and oil products. 11.108 The Kwun Mun strait was closed by cofferdams, which form the permanent protective works to the main dams. Excavation for the foundation of the West Dam was in progress. 11.109 Progress in the construction of tunnels and intakes continued satisfactorily. Raising of Plover Cove Dams, Uprating and Extension of Sha Tin Treatment Works and Pumping Station and Tai Po Tau Pumping Station 11.110 Raising of the dams and associated works at Plover Cove Reservoir were completed. Grouting to the Saddle Dam was found necessary in order to seal off seepage which was discovered when the Reservoir was filled to its top water level for the first time in September 1973. 11.111 Civil engineering works and installation of pumping plant associated with the extension of Sha Tin Treatment Works and Pumping Station were completed and the new pumpsets and clarifiers put into service. Installation of electrical and chemical plant was in hand. 11.112 At Tai Po Tau Pumping Station, installation of the pumping plants, band screens and ancillary mechanical plant was completed. Commissioning of the tunnel gates was delayed pending the delivery of the electrical switchgear from the United Kingdom. River Training Works at Tai Po 11.113 The feasibility report submitted by the consulting engineers was accepted and an item included in the Public Works Programme for its imple- mentation by the Civil Engineering Office. North Western Water Scheme - Pollution Study 11.114 The Report submitted by the consulting engineers was considered by the Public Works Sub-Committee and it was decided that because of the polluted state of the streams, no action would be taken at the present time although the potential benefits of the scheme would be kept in mind.
2026-05-12 05:53:01 · Baseline
View content

11.106

The Unit is responsible for liaising with the Consulting Engineers engaged on water supply schemes other than desalting. Expenditure during the year amounted to over $203 million.

High Island Water Scheme

11.107

Satisfactory progress was maintained despite the world-wide crisis on fuel and oil products.

11.108 The Kwun Mun strait was closed by cofferdams, which form the permanent protective works to the main dams. Excavation for the foundation of the West Dam was in progress.

11.109

Progress in the construction of tunnels and intakes continued

satisfactorily.

Raising of Plover Cove Dams, Uprating and Extension of Sha Tin Treatment Works and Pumping Station and Tai Po Tau Pumping Station

11.110

Raising of the dams and associated works at Plover Cove Reservoir were completed. Grouting to the Saddle Dam was found necessary in order to seal off seepage which was discovered when the Reservoir was filled to its top water level for the first time in September 1973.

11.111

Civil engineering works and installation of pumping plant associated with the extension of Sha Tin Treatment Works and Pumping Station were completed and the new pumpsets and clarifiers put into service. Installation of electrical and chemical plant was in hand.

11.112 At Tai Po Tau Pumping Station, installation of the pumping plants, band screens and ancillary mechanical plant was completed. Commissioning of the tunnel gates was delayed pending the delivery of the electrical switchgear from the United Kingdom.

River Training Works at Tai Po

11.113 The feasibility report submitted by the consulting engineers was accepted and an item included in the Public Works Programme for its imple- mentation by the Civil Engineering Office.

North Western Water Scheme - Pollution Study

11.114 The Report submitted by the consulting engineers was considered by the Public Works Sub-Committee and it was decided that because of the polluted state of the streams, no action would be taken at the present time although the potential benefits of the scheme would be kept in mind.

Comments

Approved members can add comments, bookmarks, and private notes.

No comments yet.

Private Research Note

Private notes are available after approval.