New Territories Administration

4.51 Departmental quarters for the New Territories Administration at Tai Po were well advanced at the end of the year in question and will be completed towards the end of 1973.

Police

4.52 Construction continued on the new headquarters building in Arsenal Street, due for completion in August 1973.

4.53 Sub-Divisional Police Stations at Ngau Tau Kok and Tsz Wan Shan were completed in April 1973 and those at Shing Wo Road and Chai Wan were at an advanced stage of construction. Piling work in connection with the North Point Divisional Station was under way.

Post Office

4.54 The first stage of improvements to the Kowloon Sorting Office was completed and the second stage, which is an extension, was put in hand.

Prisons Projects

4.55 The Dragon's Back Training Centre for 170 young offenders was completed during the year. The complex also contains staff quarters.

4.56 Quarters for married officers at Tai Lam treatment centre were finished at the end of 1972.

4.57 At Chi Ma Wan Prison, quarters were completed for warders and toilet facilities were improved in the prison dormitories.

Quarters

4.58 On Hong Kong Island 25 quarters of Type 2 were completed for government servants at Mansfield Road and extensive alterations were carried out to the flats on the Peak known as Homestead.

4.59 Site formation and construction of the sub-structure was in hand for Departmental Quarters for Uniformed Staff of the Immigration Department.

4.60 Also completed were 229 quarters at Hung Hom for married staff of the Preventive Service.

47

Edit History

2026-05-12 04:18:07 · NVIDIA / meta/llama-4-maverick-17b-128e-instruct
Live
View comparison
AI Proofread
New Territories Administration 4.51 Departmental quarters for the New Territories Administration at Tai Po were well advanced at the end of the year in question and will be completed towards the end of 1973. Police 4.52 Construction continued on the new headquarters building in Arsenal Street, due for completion in August 1973. 4.53 Sub-Divisional Police Stations at Ngau Tau Kok and Tsz Wan Shan were completed in April 1973 and those at Shing Wo Road and Chai Wan were at an advanced stage of construction. Piling work in connection with the North Point Divisional Station was under way. Post Office 4.54 The first stage of improvements to the Kowloon Sorting Office was completed and the second stage, which is an extension, was put in hand. Prisons Projects 4.55 The Dragon's Back Training Centre for 170 young offenders was completed during the year. The complex also contains staff quarters. 4.56 Quarters for married officers at Tai Lam treatment centre were finished at the end of 1972. 4.57 At Chi Ma Wan Prison, quarters were completed for warders and toilet facilities were improved in the prison dormitories. Quarters 4.58 On Hong Kong Island 25 quarters of Type 2 were completed for government servants at Mansfield Road and extensive alterations were carried out to the flats on the Peak known as Homestead. 4.59 Site formation and construction of the sub-structure was in hand for Departmental Quarters for Uniformed Staff of the Immigration Department. 4.60 Also completed were 229 quarters at Hung Hom for married staff of the Preventive Service. 47
Baseline (Original)
New Territories Administration 4.51 Departmental quarters for the New Territories Administra- tion at Tai Po were well advanced at the end of the year in question and will be completed towards the end of 1973. Police 4.52 Construction continued on the new headquarters building in Arsenal Street, due for completion in August 1973. 4.53 Sub-Divisional Police Stations at Ngau Tau Kok and Tsz Wan Shan were completed in April 1973 and those at Shing Wo Road and Chai Wan were at an advanced stage of construction. Piling work in connection with the North Point Divisional Station was under way. Post Office 4.54 The first stage of improvements to the Kowloon Sorting Office was completed and the second stage, which is an extension, was put in hand. Prisons Projects 4.55 The Dragon's Back Training Centre for 170 young offenders was completed during the year. The complex also contains staff quarters. 4.56 Quarters for married officers at Tai Lam treatment centre were finished at the end of 1972. 4.57 At Chi Ma Wan Prison, quarters were completed for warders and toilet facilities were improved in the prison dormitories. Quarters 4.58 On Hong Kong Island 25 quarters of Type 2 were completed for government servants at Mansfield Road and extensive alterations were carried out to the flats on the Peak known as Homestead. 4.59 Site formation and construction of the sub-structure was in hand for Departmental Quarters for Uniformed Staff of the Immigra- tion Department. 4.60 Also completed were 229 quarters at Hung Hom for married staff of the Preventive Service. 47
2026-05-12 04:18:07 · Baseline
View content

New Territories Administration

4.51 Departmental quarters for the New Territories Administra- tion at Tai Po were well advanced at the end of the year in question and will be completed towards the end of 1973.

Police

4.52 Construction continued on the new headquarters building in Arsenal Street, due for completion in August 1973.

4.53 Sub-Divisional Police Stations at Ngau Tau Kok and Tsz Wan Shan were completed in April 1973 and those at Shing Wo Road and Chai Wan were at an advanced stage of construction. Piling work in connection with the North Point Divisional Station was under way.

Post Office

4.54 The first stage of improvements to the Kowloon Sorting Office was completed and the second stage, which is an extension, was put in hand.

Prisons Projects

4.55 The Dragon's Back Training Centre for 170 young offenders was completed during the year. The complex also contains staff quarters.

4.56 Quarters for married officers at Tai Lam treatment centre were finished at the end of 1972.

4.57 At Chi Ma Wan Prison, quarters were completed for warders and toilet facilities were improved in the prison dormitories.

Quarters

4.58 On Hong Kong Island 25 quarters of Type 2 were completed for government servants at Mansfield Road and extensive alterations were carried out to the flats on the Peak known as Homestead.

4.59 Site formation and construction of the sub-structure was in hand for Departmental Quarters for Uniformed Staff of the Immigra- tion Department.

4.60 Also completed were 229 quarters at Hung Hom for married staff of the Preventive Service.