Project

Sai Kung Town Water Supply ... ... $3,456,000 Extension of Mains Water Supplies to Villages in the Yuen Long and Tai Po Districts ... $3,560,000 Provision of Waterworks Depots and Quarters for Distribution Staff on Peng Chau and Cheung Chau ... $280,000 Uprating Tsuen Wan Filter and Pumping Stations ... $1,500,000 Shek Pik Scheme ... ... $581,000,000 Plover Cove Stages I and II ... $263,560,000 High Island Water Scheme ... ... ... ... ... ... A ... * ... ... Raising of Plover Cove Dam and Associated Works Provision of Temporary Pumps at Tai Mei Tuk $1,348,000,000 Purchase and Installation of Experimental Desalting Plant Single Purpose Desalting Plant $180,000,000 General ... $500,000 ... : $2,000,000 ... ... $460,000,000 Improvements to staff Facilities at Waterworks Installations Minor Works Selected from Items in Category D $305,000 (3) Projects on which Consultants were engaged $135,000 Raising of Plover Cove Dams, Uprating and Extension of Sha Tin Treatment Works and Pumping Station and Tai Po Tau Pumping Station ... River Training Works at Tai Po High Island Water Scheme Experimental Desalting Plant 40 m.g.d. Single Purpose Desalting Plant Studies for dual operation of Desalting Plants Waterworks Monitoring and Control Requirements ... North Western Water Scheme-Pollution Study Examination and Report on the Safety of Reservoirs Approximate Cost

Plover Cove Scheme Joint Engineers (Messrs. Binnie and Partners with Messrs. Scott Wilson Kirkpatrick Partners) and Messrs. Binnie and Partners

211

Page 211

Edit History

2026-05-12 04:57:03 · NVIDIA / meta/llama-4-maverick-17b-128e-instruct
Live
View comparison
AI Proofread
APPENDIX BB-Contd. Project Sai Kung Town Water Supply ... ... $3,456,000 Extension of Mains Water Supplies to Villages in the Yuen Long and Tai Po Districts ... $3,560,000 Provision of Waterworks Depots and Quarters for Distribution Staff on Peng Chau and Cheung Chau ... $280,000 Uprating Tsuen Wan Filter and Pumping Stations ... $1,500,000 Shek Pik Scheme ... ... $581,000,000 Plover Cove Stages I and II ... $263,560,000 High Island Water Scheme ... ... ... ... ... ... A ... * ... ... Raising of Plover Cove Dam and Associated Works Provision of Temporary Pumps at Tai Mei Tuk $1,348,000,000 Purchase and Installation of Experimental Desalting Plant Single Purpose Desalting Plant $180,000,000 General ... $500,000 ... : $2,000,000 ... ... $460,000,000 Improvements to staff Facilities at Waterworks Installations Minor Works Selected from Items in Category D $305,000 (3) Projects on which Consultants were engaged $135,000 Raising of Plover Cove Dams, Uprating and Extension of Sha Tin Treatment Works and Pumping Station and Tai Po Tau Pumping Station ... River Training Works at Tai Po High Island Water Scheme Experimental Desalting Plant 40 m.g.d. Single Purpose Desalting Plant Studies for dual operation of Desalting Plants Waterworks Monitoring and Control Requirements ... North Western Water Scheme-Pollution Study Examination and Report on the Safety of Reservoirs Approximate Cost Plover Cove Scheme Joint Engineers (Messrs. Binnie and Partners with Messrs. Scott Wilson Kirkpatrick Partners) and Messrs. Binnie and Partners 211 Page 211
Baseline (Original)
APPENDIX BB-Contd. Project Sai Kung Town Water Supply ... Extension of Mains Water Supplies to Villages in the Yuen Long and Tai Po Districts ... Provision of Waterworks Depots and Quarters for Distribution Staff on Peng Chau and Cheung Chau Uprating Tsuen Wan Filter and Pumping Stations Shek Pik Scheme ... Plover Cove Stages I and II High Island Water Scheme ... ... A ... * ... Raising of Plover Cove Dam and Associated Works Provision of Temporary Pumps at Tai Mei Tuk Purchase and Installation of Experimental Desalting Plant Single Purpose Desalting Plant General ... : : ... ... Improvements to staff Facilities at Waterworks Installations Minor Works Selected from Items in Category D (3) Projects on which Consultants were engaged Raising of Plover Cove Dams, Uprating and Extension of Sha Tin Treatment Works and Pumping Station and Tai Po Tau Pumping Station ... River Training Works at Tai Po High Island Water Scheme Experimental Desalting Plant 40 m.g.d. Single Purpose Desalting Plant Studies for dual operation of Desalting Plants Waterworks Monitoring and Control Require- ments ... North Western Water Scheme-Pollution Study Examination and Report on the Safety of Reservoirs Approximate Cost $ 3,456,000 3,560,000 280,000 1,500,000 581,000,000 263,560,000 ... 1,348,000,000 ... 180,000,000 500,000 2,000,000 460,000,000 305,000 135,000 Plover Cove Scheme Joint Engineers (Messrs. Binnie and Partners with Messrs. Scott Wilson Kirkpatrick Partners) and Messrs. Binnie and Partners 211
2026-05-12 04:57:03 · Baseline
View content

APPENDIX BB-Contd.

Project

Sai Kung Town Water Supply ...

Extension of Mains Water Supplies to Villages in the Yuen Long and

Tai Po Districts

...

Provision of Waterworks Depots and Quarters for Distribution Staff

on Peng Chau and Cheung Chau

Uprating Tsuen Wan Filter and Pumping Stations

Shek Pik Scheme ...

Plover Cove Stages I and II

High Island Water Scheme

...

...

A

...

*

...

Raising of Plover Cove Dam and Associated Works Provision of Temporary Pumps at Tai Mei Tuk Purchase and Installation of Experimental Desalting Plant Single Purpose Desalting Plant

General

...

:

:

...

...

Improvements to staff Facilities at Waterworks Installations Minor Works Selected from Items in Category D

(3) Projects on which Consultants were engaged

Raising of Plover Cove Dams, Uprating and Extension of Sha Tin Treatment Works and Pumping Station and Tai Po Tau Pumping Station ...

River Training Works at Tai Po

High Island Water Scheme

Experimental Desalting Plant

40 m.g.d. Single Purpose Desalting Plant Studies for dual operation of Desalting Plants Waterworks Monitoring and Control Require-

ments

...

North Western Water Scheme-Pollution Study Examination and Report on the Safety of

Reservoirs

Approximate Cost

$

3,456,000

3,560,000

280,000 1,500,000 581,000,000

263,560,000

...

1,348,000,000

...

180,000,000

500,000 2,000,000

460,000,000

305,000 135,000

Plover Cove Scheme Joint Engineers (Messrs. Binnie and Partners with Messrs. Scott Wilson Kirkpatrick Partners)

and

Messrs. Binnie and Partners

211

Comments

Approved members can add comments, bookmarks, and private notes.

No comments yet.

Private Research Note

Private notes are available after approval.