APPENDIX X
HIGHWAYS OFFICE
NEW HIGHWAYS PROJECTS COSTING OVER $100,000 COMPLETED IN THE FINANCIAL YEAR 1972-73
Project Approximate Cost $ (a) Roadworks, Drainage and Bridges (i) Hong Kong Temporary Car Parking Area, Ex-Naval Dockyard, Harcourt Road 253,000 Protection of Godown Areas and Vegetable Market at West Point 202,000 Connaught Road Central Widening (from Queen Victoria Street to Murray Road) 4,500,000 Connaught Road Central Widening (from Queen Victoria Street to Morrison Street) 2,080,000 Flyovers at Upper Albert Road/Garden Road/Kennedy Road Junction 2,607,000 Pokfulam Road/Hill Road/Bonham Road junction Improvement 4,473,000 Sewer Extension for Watford Road Development, Magazine Gap 180,000 Construction of New Road and Ancillary Works on Tai Tam Road leading to RBL 821, Red Hill 700,000 Vehicular Access Bridge for Upper Level Police Station-High Street 158,000 Cross Harbour Tunnel Road Connections, Island 5,546,000 Cross Harbour Tunnel Road Connections, Traffic and Directional signs 703,000 Barker Road Widening Adjoining RBL 862 189,000 (ii) Kowloon Argyle Street/Waterloo Road/Princess Margaret Road Junction Improvements 192,000 Shatin Pass Road Reconstruction 1,220,000 Tai Kok Tsui Road Extension (Fuk Tsuen Street to Cherry Street) 500,000 Lei Yue Mun Road Interim Improvement (from Junk Bay Road to Yau Tong Road) 524,000 West Kowloon Corridor-Stage I-Elevated Road-Gascoigne Road to Tong Mi Road-Site Investigation 110,000 Argyle Street Improvements, Stage II (Tin Kwong Road to Kowloon City Roundabout) 600,000 Prince Edward Road Improvement, Stage II (Earl Street to Short Street) 1,100,000 Boundary Street/Tai Hang Tung Road Junction Improvements 480,000200
APPENDIX X
HIGHWAYS OFFICE
NEW HIGHWAYS PROJECTS COSTING OVER $100,000 COMPLETED IN THE FINANCIAL YEAR 1972-73
Project
(a) Roadworks, Drainage and Bridges
(i) Hong Kong
Temporary Car Parking Area, Ex-Naval Dockyard, Harcourt
Road
Approximate Cost
$
253,000
Protection of Godown Areas and Vegetable Market at West
Point
202,000
Connaught Road Central Widening (from Queen Victoria Street
to Murray Road)...
4,500,000
Connaught Road Central Widening (from Queen Victoria Street
to Morrison Street)
...
...
2,080,000
...
...
Flyovers at Upper Albert Road/Garden Road/Kennedy Road
Junction
►
2,607,000
Pokfulam Road/Hill Road/Bonham Road junction Improvement 4,473,000 Sewer Extension for Watford Road Development, Magazine Gap Construction of New Road and Ancillary Works on Tai Tam
Road leading to RBL 821, Red Hill
180,000
...
700,000
Vehicular Access Bridge for Upper Level Police Station-High
Street
158,000
Cross Harbour Tunnel Road Connections, Island
5,546,000
...
Cross Harbour Tunnel Road Connections, Traffic and Direc-
tional signs
...
..
703,000
Barker Road Widening Adjoining RBL 862
189,000
(ii) Kowloon
Argyle Street/Waterloo Road/Princess Margaret Road Junction
Improvements
192,000
Shatin Pass Road Reconstruction
1,220,000
•
Tai Kok Tsui Road Extension (Fuk Tsuen Street to Cherry
Street)
500,000
Lei Yue Mun Road Interim Improvement (from Junk Bay Road
to Yau Tong Road)
...
...
...
524,000
West Kowloon Corridor-Stage I-Elevated Road-Gascoigne
Road to Tong Mi Road-Site Investigation
110,000
Argyle Street Improvements, Stage II (Tin Kwong Road to
Kowloon City Roundabout)
600,000
...
•
Prince Edward Road Improvement, Stage II (Earl Street to Short
Street)
1,100,000
Boundary Street/Tai Hang Tung Road Junction Improvements
480,000