day desalting plant, owing to the very heavy commitments of the Chief Engineer (Construction).
Planning Works
11.37 The joint inspection, by this Division and Messrs. Binnie & Partners, of impounding and service reservoirs exceeding ten million gallons in capacity continued. In October, Supply Division assumed responsibility for this work.
11.38 The study on the distribution of water in the Wan Chai and North Point districts was completed, and detailed consideration was given to the pumping requirements at North Point to boost supplies from the North Point cross harbour main.
11.39 Proposals for improvement of the Central District salt water flushing system and the Pokfulam fresh water system were finalized. The possibility of using part of Mt. Davis primary service reservoir for general supply purposes was studied.
11.40 A recommendation was made for the extension of the Sau Mau Ping salt water flushing system to supply high level developments at Ngau Chi Wan, Hammer Hill, Shun Lee Tsuen, Sau Mau Ping and Lam Tin.
11.41 Preliminary studies on the reprovisioning of the existing workshops and depot facilities were completed.
11.42 Following the investigation into the silting and pollution of Jordan Valley and Ma Lau Tong flushing reservoirs, proposals were made for improvement of the quality of supplies from these sources.
11.43 The study on the optimum development of the minor catchments was completed and proposals were circulated to departments concerned for comments.
11.44 A scheme to supply the high level developments at Lai Chi Kok Ridge was prepared.
11.45 Preliminary supply proposals were prepared for the Tsuen Wan/Kwai Chung North and Tsing Yi Island development.
11.46 An analysis of the adequacy of fresh water trunk mains to distribute future resources was approaching completion, and investigation into the primary service storage requirement at Lion Rock commenced.
149
1
day desalting plant, owing to the very heavy commitments of the Chief Engineer (Construction).
Planning Works
11.37 The joint inspection, by this Division and Messrs. Binnie & Partners, of impounding and service reservoirs exceeding ten million gallons in capacity continued. In October, Supply Division assumed responsibility for this work.
11.38 The study on the distribution of water in the Wan Chai and North Point districts was completed, and detailed consideration was given to the pumping requirements at North Point to boost supplies from the North Point cross harbour main.
11.39 Proposals for improvement of the Central District salt water flushing system and the Pokfulam fresh water system were finalized. The possibility of using part of Mt. Davis primary service reservoir for general supply purposes was studied.
11.40 A recommendation was made for the extension of the Sau Mau Ping salt water flushing system to supply high level developments at Ngau Chi Wan, Hammer Hill, Shun Lee Tsuen, Sau Mau Ping and Lam Tin.
11.41 Preliminary studies on the reprovisioning of the existing workshops and depot facilities were completed.
11.42 Following the investigation into the silting and pollution of Jordan Valley and Ma Lau Tong flushing reservoirs, proposals were made for improvement of the quality of supplies from these sources.
11.43 The study on the optimum development of the minor catch- ments was completed and proposals were circulated to departments concerned for comments.
11.44 A scheme to supply the high level developments at Lai Chi Kok Ridge was prepared.
11.45 Preliminary supply proposals were prepared for the Tsuen Wan/Kwai Chung North and Tsing Yi Island development.
11.46 An analysis of the adequacy of fresh water trunk mains to distribute future resources was approaching completion, and investigation into the primary service storage requirement at Lion Rock commenced.